Line reopened weekdays between Dover and Folkestone following sea damage

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

wimbledonpete

Member
Joined
25 Nov 2011
Messages
260
Guard this evening told everyone for Dover-Sandwich to travel in the front 6, because the rear 6 would be locked out of use after Folkestone "because Shakespeare Tunnel can only take 6 coaches". Is this because of the single bore and problems with emergency evacuation?
 

Cletus

Established Member
Joined
11 Dec 2010
Messages
2,399
Location
Dover
Guard this evening told everyone for Dover-Sandwich to travel in the front 6, because the rear 6 would be locked out of use after Folkestone "because Shakespeare Tunnel can only take 6 coaches". Is this because of the single bore and problems with emergency evacuation?

Yes it is.
 

MrB

Member
Joined
3 Jan 2016
Messages
389
Location
London
Guard this evening told everyone for Dover-Sandwich to travel in the front 6, because the rear 6 would be locked out of use after Folkestone "because Shakespeare Tunnel can only take 6 coaches". Is this because of the single bore and problems with emergency evacuation?

I assume that this means all the interconnecting gangway doors were shut or is there another way of locking the units OOU.

In addition, was this procedure in place before the line closed or not?
 

Hophead

Established Member
Joined
5 Apr 2013
Messages
1,400
I assume that this means all the interconnecting gangway doors were shut or is there another way of locking the units OOU.

In addition, was this procedure in place before the line closed or not?

A front 6 sounds to me like a pair of 395s, so no interconnecting doors to worry about
 

LewFinnis

Member
Joined
22 Aug 2013
Messages
107
South Eastern website gives closure this weekend (10/11) between Ashford and Dover and the following Sunday (19) between Ebbsfleet and Ashford; nothing the following weekend. Could change, I suppose.
 

Southern

Member
Joined
19 Jun 2005
Messages
527
Location
Folkestone, Kent
Well it's now Day 3 of the line being reopened and with it the return of the unreliable St Pancras - St Pancras loop...

A great idea in theory but one that, in practice, just doesn't work very well. I know it's only been open again since Monday but I remember this happening last summer, when half of the country decided to flock to Margate and the announcement "delayed due to an unusually large passenger flow" was the norm on the coast. The reason for the delays this week aren't clear but the loop in both directions has returned to 5-10 minute late running on arrival at Folkestone, in both directions.
 
Last edited:

Cletus

Established Member
Joined
11 Dec 2010
Messages
2,399
Location
Dover
For information, the path and bridge down to Shakespeare beach re-opened today.

https://www.networkrailmediacentre....l-to-celebrate-reopening-of-shakespeare-beach

For decades, Channel swimmers have begun their epic journeys towards France from Shakespeare Beach in Dover. Now for the first time since Boxing Day 2015, when a massive storm damaged the sea wall behind the beach and the railway above it, swimmers can return to the shingle shore and enjoy one of Dover’s hidden gems after a new footbridge restored access to the beach.

Network Rail engineers were today joined by Dover MP Charlie Elphicke and members of the Channel Swimming Association to officially open the bridge and mark the completion of a mammoth project to rebuild the sea wall protecting the railway between Dover and Folkestone.

Repairs began in January 2016, when the first of 90,000 tonnes of granite rock armour was delivered to site. Since then, Network Rail engineers have been working to place the rock armour along a 375m stretch of the wall and put the new footbridge in place across the railway and down to the beach.

The railway and sea wall itself were opened in September 2016.

Network Rail’s director of route asset management, Alan Ross, said: “We knew from the minute we arrived in Dover on Boxing Day 2015 that this was going to be a huge job. We not only had to rebuild and protect the railway between Dover and Folkestone, but we also had to protect the cliff itself.

“It’s great news for the local community that the beach is back open and I’d like to thank them for their support and understanding while we carried out our work. I’ve never known a project where everyone in the area has helped and supported us in the way that Dover did, from MP Charlie Elphicke to Dover District Council and businesses and people in the town.

“We all felt responsible for making this project as good as it could be and finally we can say we’ve achieved our aim and the beach is back open.”

Dover and Deal MP Charlie Elphicke, who chaired the sea wall repair task force after the storm of Christmas 2015, said: “Our fight to fix the sea wall just goes to show what can be achieved if people work together and get on with the job. Dedicated workers from Network Rail and Costain grafted round the clock – and the rail line was back on track three months ahead of schedule.

“It’s fantastic to see the new footbridge and the historic Shakespeare Beach reopen today. I’m delighted our incredible Channel swimmers have now got their beach back.”

Michael Read, who is president of the Channel Swimming Association and has swum the Channel 33 times, said: “I’m delighted that the beach is back because it was always the traditional starting point for swims and Channel swimmers have such an affection for it. Over the years we have also been able to use Samphire Hoe and now the pilots can choose a beach depending on the tides and how they will affect the swimmer.

“The feeling of completing a crossing and walking back on dry land is the most wonderful feeling in the world.”

Tim Ingleton, Dover District Council’s Head of Inward Investment, said: ““We are very pleased to hear this news from Network Rail, and welcome the completion of this important work, which will reconnect Shakespeare Beach with the community.”

The project to rebuild the railway and part of the sea wall at Shakespeare Beach began immediately after Christmas 2015 and cost £39.8m. More than 90,000 tonnes of rock armour was shipped to Dover by barge, arriving at the port and latterly on a barge anchored offshore.

The railway was rebuilt on a 235m viaduct supported by 138 columns and the rock armour was arranged along the beach to protect both it and the cliff face behind it from the power of the sea.

At its peak, more than 1,000 people worked on the project at Dover, with around 150 working on the beach works and the footbridge. Companies involved were Network Rail and principle contractor Costain, along with Suttles Projects, who opened their quarry the day after Boxing Day, Tony Gee and Partners, who designed the viaduct; Brett, concrete; Pipex, footbridge; FP McCann, steps to the beach; Ovenden, beachworks; and Stema Shipping UK, rock supply. All told more than 180 suppliers helped bring the project to completion.
 