As far as I can see, all the loaded biomass trains run into Tuebrook sidings and reverse there to access the L&M.
Eastbound empty trains do use the Olive Mount Chord.
So the Chord gets less use than you might think.
Earlestown West Jn was recently upgraded, and I can't see the potential for any further major improvements.
The Huyton 4th track will certainly help.
Which begs the questions, how many intermodal trains a day might realistically be required, assuming the rail infrastructure could accomodate them? And which terminals around the country might they serve?Running intermodal trains from Seaforth to the same railheads around the country as used by services from Felixstowe, London Gateway and Southampton would reduce the problem and allow the shipping lines and hauliers to maximise on their existing road transport infrastructure.
Intermodal rail freight has, I understand, only been successful over distances of hundreds of miles or more. So, to take one example, intermodal trains currently carry containers from Southampton, Felixstowe and London Gateway to Trafford Park near Manchester for distribution by road around North West England. However, trains from Liverpool to Trafford Park are unlikely to be viable - it will be quicker and cheaper to use road transport direct from Liverpool.
In the other direction, do you envisage trains from Liverpool to the South East and South, competing with the southern ports in their "home market"? That might be a bit ambitious. North East England and Scotland might be more realistic. But how would volumes compare with the local market in the North West?
Can the Ship Canal play a significant role in relieving Liverpool's road network, via feeder services between Peel's Liverpool 2 and Port Salford facilities?
Yes they do on the 2400 tonnes trains (which most are anyway) and the banker becomes the leading loco out of Tuebrook Sidings to Drax AES. It is an easier and more practicable option than double heading. Likewise, going via Northwich etc avoids double heading too and not using the OLive Mount Chord in consequence.Does the biomass have banker from the docks?
if so, the use of Tuebrook makes sense to release the train engine and continue with the banker leading.
See above - banker becomes lead loco from Tuebrook Sdgs.Yes, I believe they make use of a banker which is released at Tuebrook.
Liverpool's hey day as a port was when trade was with the Americas, Africa and the Far East. Arguably the increased trade with Europe after joining the EU combined with other factors had a negative impact on the prospects of the port. The continued development of S Eastern ports where Container ships made calls in Europe and the UK locked Liverpool out of this market. However with trade now shifting (shifted) back to the Far East and the Americas and ships getting bigger and bigger if those massive intercontinental ships make one or two European Calls with feeder services serving other local ports then the Geographical location of Liverpool's port could well play to its advantage as it did historically. So yes, quite possibly, Liverpool2's hinterland could given time to develop push down into the South and South Eastern Markets, however this can only be successful if the rail infrastructure allows it.
Although a new member here I have been lurking for a long time and have followed the various discussions about the Port of Liverpool with some interest. This paragraph certainly sums up my own view of Liverpool's history very well.
Looking ahead the question is partly about the comparative rail capacity available out of different ports. Work has already been done to improve capacity out of Felixstowe with more to follow, though at some point the Felixstowe branch itself will surely be full. Likewise the Electric Spine (if it gets going) should allow more trains in/out of Southampton. With relatively few trains running out of Liverpool do we really know what the capacity constraints are? And there may also be the danger that Liverpool becomes the west coast's mirror image to the east coast's Immingham, ie rail can win the specialist bulk hauls but the boxes all go by road.
................... With relatively few trains running out of Liverpool do we really know what the capacity constraints are? And there may also be the danger that Liverpool becomes the west coast's mirror image to the east coast's Immingham, ie rail can win the specialist bulk hauls but the boxes all go by road.
I did not intend to imply that containers would be trucked from Liverpool to Trafford Park. They would, as you say, go direct by road to the final destination.Agreed, I don't think we will see rail traffic to Trafford Park, but then I don't see many containers going from Liverpool to Trafford Park. Why would you do that when you can distribute it straight to its final destination? The only reason Trafford park exists is as a distribution point for containers dragged up the rails from the South. The usage of Trafford Park could indeed fall with the other developments and the potential to distribute the containers it currently handles directly from the port.
I suspect that the Midlands and North Wales are also too close to Liverpool for rail transshipment to be competitive with direct road distribution. And these regions, together with North West England, are where the southern ports are most vulnerable to competition from Liverpool, due to geography. So if Liverpool succeeds in capturing these flows, it will mean more lorries on Liverpool's roads, not more trains from the Port.That is already included in the plans. Peel are developing the Port Salford facilities with the intention of running feeder services up the ship canal. They are also looking at feeder services up to Glasgow and across the Irish Sea to Dublin and Belfast. You are right to identify the North East and Yorkshire, I would also say the East and West Midlands. However pushing futher South and East into Felixstowe and Southampton and London Gateway's market is certainly a possibility in the longer term.
Agreed. Although a silver lining would be that a decline in intermodal rail freight, particularly to Trafford Park via Manchester Oxford Road, would free up capacity for additional passenger services.Sadly, I believe there is more than a MAY about this.
Rail succeeds out of the current big four because they are at one end of the country giving longer rail hauls.
Immingham and Liverpool are in the centre putting many more trips within the radius of road haulage and making the critical mass required for rail harder to achieve.
Instead of reducing road miles, I fear that feeder ships to Liverpool will increase them as traffic is abstracted from rail.
I suspect that the Midlands and North Wales are also too close to Liverpool for rail transshipment to be competitive with direct road distribution. And these regions, together with North West England, are where the southern ports are most vulnerable to competition from Liverpool, due to geography. So if Liverpool succeeds in capturing these flows, it will mean more lorries on Liverpool's roads, not more trains from the Port.
Intermodal trains from Liverpool to Doncaster, Wakefield and Leeds, which currently have flows from the southern ports, would compete for paths on the congested transpennine lines, while trains to London would need paths on the WCML. So if the Liverpool local infrastructure were to be further upgraded to allow more than the planned 48 daily paths from the Port, would it really be possible to make use of them? Or are the pinch-points elsewhere on the network a higher priority?
Rail succeeds out of the current big four because they are at one end of the country giving longer rail hauls.
Immingham and Liverpool are in the centre putting many more trips within the radius of road haulage and making the critical mass required for rail harder to achieve.
Instead of reducing road miles, I fear that feeder ships to Liverpool will increase them as traffic is abstracted from rail.
There is no current capacity rail restraints in and out of Liverpool Docks as the paths are there but with the exception of the "Biomass" traffic, the odd scrap train, there is no traffic. For "liner" trains to operate in and out of the docks, the infrastruture needs updating and extending to facilitate much longer trains (then they become economically viable) but sadly there is no current indication by Peel Ports to do that! Likewise, with Stobarts Widnes Terminal down the road so to speak, then containers can continue to go there and back by road - quicker and cheaper than rail. Peel Ports emphasis is move "containers" by water were possible, therefore various points down the Manchester Ship Canal is part of that plan. Also money has been allocated by DoT to improve the main thoroughfare between Seaforth and the M57/M58 at Switch Island for road traffic.
Yes I agree about Liverpool Docks becoming (to a lesser extent) a mirror image of Immingham as I am not that optimistic with current speak from Peel Ports about rail container operations. If it happens, it will be a slow process and that will depend on a lot of "non" rail related factors changing or happening first.
Sorry I don't understand why the Midlands (Birmingham at ~100 miles by road) (Nottingham ~120 miles by Road) are not suitable for rail whilst Leeds (80 miles by road) would be.
There are undoubtedly other pinch points, I have pointed out in another place that given the proportion of Liverpool freight that loops all the way around the South of Manchester to cross the Pennines via Todmordon, it would make a lot more sense if the infrastructure was adapted to allow cross Pennine freight to avoid the Manchester area all together and go via Ormskirk, Blackburn and Burnley.
As to whether the Port could make use of 48+ paths, that is obviously linked to the number and size of ships that the port can attract, which in turn is linked to the speed and size of the Ports Hinterland. It doesn't necessarily need to have quicker/easier access to specific markets that the southern ports currently serve, it just that is needs to have quick enough access on average to a large enough market that it makes sense for Liverpool to be the deep water port of choice for UK wide distribution. Given it will clearly be in a good position to capture the North West (by road), Ireland/Northern Ireland and the Scottish Central Belt (by water) and a have a good chance of competing with Felixstowe, Southampton etc. for South Wales, Yorkshire, The North East and West Midlands by Rail, eventually a tipping point will be reached where it may be more economical for a shipping company to land all of their intercontinental Inter-modal Freight for the UK and Ireland at Liverpool. Given at the same time there is an increase in the number of passenger services looking at using the via Huyton route out of Lime Street, by the time it gets to the point where the port is competitive in this market, it will find it increasingly difficult. 48 paths may be OK initially but many many more could be opened up with a couple of relatively straight forward and simple local projects. At which point the port has a good chance of competing rather than having its obvious potential curtailed.
Who are the smaller operators you refer too?.................What I suspect we may see it in the short term is a small number of trains being operated by the smaller operators for individual road hauliers such as the test train operated just before Christmas, beyond this it is anyone's guess. ............
Who are the smaller operators you refer too?DBC, Freightliner, GBRf, DRS are not exactly small although the order I've put them in, is probably about right who is the largest from the first name DBS down to DRS. The only other player is Colas who may be termed as a smaller operator in the UK, may be DCR (I think) who are based in the south but that is about it.
GBRf operated the "test" train in December from the docks are not exactly small to be honest but along with them, I reckon only "Freightliner" would do business with Liverpool for any "liner / intermodal" traffic.
Indeed this the existing model which of course stems from the decision by the shipping lines converting to container operations in the late 1960's using Felixstowe, Southampton and Tilbury decided it was more cost advantageous to them. It was claimed at the time that the deviation to Liverpool would be too costly amongst compared to the cost of moving containers north /south especially as the shipping lines subsidised part of the cost of the movement in most cases. Forty years later the extra cost of the deviation to Liverpool is by comparison considerably less due to the use of more efficient diesel engines, relatively cheap fuel and of course the greater number of containers carried by each vessel. Let us not forget that the first ships sailing to Australia in 1969 were just 1000 teu and by 1972 they were 2500 teu, which is the size of the feeder vessels now being used by the carriers serving Liverpool today. Today the freight revenue is often less than the cost of moving a laden container by rail from Felixstowe to Manchester, so the carriers no longer have the option to subsidise the cost and thus it becomes more advantageous to take the ship to the cargo instead of the reverse.
I understand your thoughts on this but I have a problem.
The very large container carriers deployed on round the world services do not simply make a single call in the UK and then return to the Far East or wherever. They make one call in the UK and one or two more in continental Europe.
They will not make a second call in the UK so Liverpool would have to be instead of one of the southern ports not as well as. Additionally, most of the containers on the ship are not for the UK but elsewhere. Therefore, the majority of the containers will be taken on a two day jaunt up the Irish sea before going to Rotterdam or wherever.
I can see Liverpool winning additional feeder services, possible direct from the likes of Rotterdam at the expense of Felixstowe etc, but I just cannot see Liverpool replacing any of the big four as the only UK call.
And why don't you quote the whole sentence rather than just a select part as your reply has taken it out of context!I wouldn't bet on that one. With the loss of coal traffic and recent changes in contracts on other flows, some FOCS are actively chasing other market opportunities.
The biomass trains from Liverpool conform to the "go anywhere" W6A loading gauge. However, intermodal trains need gauge clearance to W10/W12, in order that standard High Cube containers can be carried on standard flat wagons. The current W10/W12 cleared network mainly radiates from the southern ports, for obvious reasons. None of the transpennine lines are currently W10/W12 cleared, so a container train from Liverpool to the E Midlands or North East would have to be routed south on the WCML to Lichfield Trent Valley, then back north via Burton-on-Trent!
The Diggle line will no doubt be cleared to W10/W12 as part of the electrification upgrade, when that eventually happens. However, intermodal trains from Liverpool would have to be routed either through central Manchester or via Crewe and Wimslow, and there are likely to be few paths available, except at night.
What is really needed is W10/W12 clearance of both the Calder Valley and Hope Valley lines, together with the Mid-Cheshire line from Hartford to Guide Bridge via Stockport and to Chinley via Hazel Grove (to bypass Manchester and Crewe). But gauge clearance work is not quick or cheap. For example, the Mid-Cheshire line has many brick arch overbridges, which would all have to be raised or replaced.
Improvements to the Bootle branch will bring little benefit unless the rest of the rail network can provide the capacity for the extra trains to get to their final destinations. But I guess it would be less palatable to the Merseyside electorate if local politicians were to demand investment in the rail lines of Cheshire, Greater Manchester, Yorkshire and Derbyshire!
I wouldn't bet on that one. With the loss of coal traffic and recent changes in contracts on other flows, some FOCS are actively chasing other market opportunities.
RTT shows 18.24 departure from LBT across Chat Moss then via Piccadilly to Guide Bridge(reverse),Brewery Jn up to Castleton Goods loop where a loco looks to be detached and returned to LBT at 23.01,6e27 headed east at 22.45.
Wonder why this didn't run via Victoria...seems to be double headed from LBT..??...or from Guide Bridge..??
If you are interested 6E27 operated tonight via Tuebrook Sdgs headed by 66745 with 66701 (I think) on the tail crossing Sankey Viaduct heading to Manchester Piccadilly and Guide Bridge.Thanks for the info ,Doug....RTT shows a stop at Tuebrook(19.01-19.06) then a further reversal at Guide Bridge..probably double headed through to Castleton goods loop where a loco was detached..seems an unusual procedure
How does it get from Guide Bridge to Castleton?
Possibly.
Piccadilly to Guide Bridge Engineering Sidings
Reverse from Guide Bridge Engineering Sidings to Denton Junction to regain original route from Heaton Norris Junction
Reverse (although I am not sure how) and follow original route from Denton Junction to Ashton Moss North Junction and thence to Castleton.
Were there engineering works on the WCML,CLC or at Edgeley?
Not sure why they are not routed via Manchester Victoria though - much simpler!
Sunday? Ordsall Chord works? I don't think anything was going over the Trinity Way Viaduct on Sunday. Plus TPE trains from the airport were doing the Salford Crescent reverse, so it was all a bit of a mess.