Great Western Electrification Progress

Status
Not open for further replies.

hwl

Established Member
Joined
5 Feb 2012
Messages
8,234
I thought GWR was supposed to be introducing new trains as soon as next year on the stretch to Reading, so Maidenhead would need to be done by then, not waiting for Crossrail?

There is a difference between electric trains to/through Maidenhead and the works at Maidenhead being completed because crossrail work involves lots of platform and siding work too (a hang over from being the original most western terminus).
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

smiffy9373

Member
Joined
16 Apr 2016
Messages
47
387 running between Paddington and Hayes now scheduled for July as long as GTR can get there 700s into service.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
The Hendy milestones don't help much.
The Crossrail project only has the final date of Dec 2019 for the introduction of full services to Reading.
All their other milestones are for infrastructure east of Airport Jn.

Before Crossrail was extended to Reading, the milestone for through trains to Maidenhead was also the only one in Crossrail's published info for the west side, other than the 4 tph Connect running into the high level station.

I have seen no indications that Crossrail intended to introduce any sort of partial service to some intermediate station on the GW, so I'd expect their Reading through service milestone just replaced their original Maidenhead one.

Their 5 main phases are currently:
1. Shenfield to Liverpool St high level with new 345s in May 2017
2. Heathrow (replaces Connect at 4 tph) to Paddington high level May 2018
3. Abbey Woood to Paddington low level (reversing at Westbourne Park) Dec 2018
4. Shenfield to Paddington low level (reversing as above) May 2019
5. Heathrow and Reading through central core Dec 2019
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
May I just ask, has that got any relation to this 12 coach 387 saga that is currently occuring or has recently ocurred?

The "12 car saga" is about 387/2s and Gatwick Express. However the 387/1s that will come to GWR are already running in 12 car sets routinely on Thameslink.

I think they are separate issues and the former is nothing to do with cascade of trains to GW, that is caused by slight delays with 700s.
 

reddragon

Established Member
Joined
24 Mar 2016
Messages
3,271
Location
Churn (closed)
I noticed that last night wires went up on the relief lines through Pangbourne Station.

I will get out & check the wiring limits when I get a chance, but this indicates that all 4 tracks are now complete from Purley on Thames to Lower Basildon.

The secondary fixings all seem to be ready on the fast tracks through Tilehurst too, so maybe some wiring action here soon too, in addition to the return cables
 

jimm

Established Member
Joined
6 Apr 2012
Messages
5,274
I noticed that last night wires went up on the relief lines through Pangbourne Station.

I will get out & check the wiring limits when I get a chance, but this indicates that all 4 tracks are now complete from Purley on Thames to Lower Basildon.

The secondary fixings all seem to be ready on the fast tracks through Tilehurst too, so maybe some wiring action here soon too, in addition to the return cables

It's only the Reading-bound relief line that is fully wired through Pangbourne station at present. The other relief still isn't complete.

Other observations from a trip to Reading today. Most portals at Didcot are now in place, but there's still a gap below the National Grid lines. And still one missing at Goring.

Wiring-wise, apart from Pangbourne, a start has been made on heading north from Lower Basildon to fill the gap towards Goring, including across the Thames at Gatehampton bridge. Some tensioning arms are now fitted at Moulsford bridge and quite a lot of return cabling is also in place further north towards Moreton cutting.
 

itfcfan

Member
Joined
7 May 2011
Messages
346
387 running between Paddington and Hayes now scheduled for July as long as GTR can get there 700s into service.

Am I right in thinking the new Paddington-Hayes service is due to run in the path of the Paddington-Greenford service (which is due to be cut back to operate West Ealing-Greenford)?

If that's the case, isn't the new Paddington-Hayes service also contingent on the new bay platform at West Ealing being completed? Last time I went past West Ealing (~2 weeks ago) it looked like that was still some way off...
 

MarlowDonkey

Established Member
Joined
4 Apr 2013
Messages
1,824
There is a difference between electric trains to/through Maidenhead and the works at Maidenhead being completed because crossrail work involves lots of platform and siding work too (a hang over from being the original most western terminus).

Is it still planned to banish the Marlow branch trains at Maidenhead to a new build platform 6?
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,234
Am I right in thinking the new Paddington-Hayes service is due to run in the path of the Paddington-Greenford service (which is due to be cut back to operate West Ealing-Greenford)?

If that's the case, isn't the new Paddington-Hayes service also contingent on the new bay platform at West Ealing being completed? Last time I went past West Ealing (~2 weeks ago) it looked like that was still some way off...

Indeed it isn't just the stock cascade running late! My view is that it is far better to wait a few months till the infrastructure is properly finished rather than have closures every (rather then just quite few) weekends to get it finished.

On the 700 thread 377/5 has confirmed the current plan is that the Paddington - Hayes service will start with the new built GWR 387 which puts it few months away as the first unit is still in the factory.
 

RobShipway

Established Member
Joined
20 Sep 2009
Messages
3,337
Indeed it isn't just the stock cascade running late! My view is that it is far better to wait a few months till the infrastructure is properly finished rather than have closures every (rather then just quite few) weekends to get it finished.

On the 700 thread 377/5 has confirmed the current plan is that the Paddington - Hayes service will start with the new built GWR 387 which puts it few months away as the first unit is still in the factory.

I don't think that you will see any of the new 387/1 fleet much before August/September, ready to be in service by December 2016 at the earliest.
 

jimm

Established Member
Joined
6 Apr 2012
Messages
5,274
Observations from today.

As noted by reddragon, all wires up through Pangbourne station now.

Overhead metalwork in the Didcot area is now complete, with a portal under the National Grid lines in place, and I think the last portal in Goring was up as well - wasn't paying proper attention as we went past. At any rate, I think all the steelwork needed for the test section is there at last.

Both the fast lines are now wired from just north of Cholsey to just south of South Moreton and both fast lines also wired between the north end of Goring and the north end of South Stoke. Relief lines also wired along both these sections of the line.
 

WatcherZero

Established Member
Joined
25 Feb 2010
Messages
10,272
Rail has an interview with NR, saying they are on schedule for wires to be live to Bristol in September and Cardiff a year later. Its also coming in within the £2.2-£2.6bn revised budget.
 

Domh245

Established Member
Joined
6 Apr 2013
Messages
8,426
Location
nowhere
Rail has an interview with NR, saying they are on schedule for wires to be live to Bristol in September and Cardiff a year later. Its also coming in within the £2.2-£2.6bn revised budget.

This September? That'd be hugely impressive if that were the case.
 

tpm

Member
Joined
9 Jun 2015
Messages
17
Location
Bristol
Rail has an interview with NR, saying they are on schedule for wires to be live to Bristol in September and Cardiff a year later. Its also coming in within the £2.2-£2.6bn revised budget.

Presumably that's "just" Bristol Parkway though? Did they mention anything about Temple Meads?
 

MarkRedon

Member
Joined
16 Sep 2015
Messages
292
Rail has an interview with NR, saying they are on schedule for wires to be live to Bristol in September and Cardiff a year later. Its also coming in within the £2.2-£2.6bn revised budget.

September of the wrong year for Parkway! Just the beginnings of an operational electrified railway this year...
See http://www.railmagazine.com/news/network/2016/05/11/great-western-wires-in-use-by-september
...the first section of electrified track to be completed on the Great Western Main Line will be between Reading and Didcot at the end of September this year. This 16-mile section will act as a test track to allow NR to gain experience and for the Class 800/801 trains to be tested.

If NR meets its targets the wires should be up and operational to Wootton Bassett, Bristol Parkway, Cardiff and Newbury by December 2018, with Bath following at the end of April 2019, Oxford by June 2019, Bristol Parkway to Bristol Temple Meads by the end of July 2019, and to all platforms at Bristol Temple Meads by the end of April 2020. A date for the wires to reach Swansea is still to be confirmed.
- See more at: http://www.railmagazine.com/news/ne...ires-in-use-by-september#sthash.ogp6rjfF.dpuf
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,897
Location
Mold, Clwyd
Presumably that's "just" Bristol Parkway though? Did they mention anything about Temple Meads?

The interview just repeats the Hendy dates (Dec 2018 to Bristol Parkway/Cardiff/Newbury, later to Bristol TM/Oxford).
But these are "infrastructure complete" dates, not "first electric train".
The "September" date relates to the Reading-Didcot test section later this year.

They are also aiming for Paddington-Maidenhead by the May 2017 timetable change, but that is ahead of the Hendy date (end-June).
It's like a lot of Rail interviews, it reads very positively but doesn't really add much to official statements.
Apparently the HOPS system is doing better at 12-14 piles a night.

There are also remarks that ETCS will be installed to Heathrow/Reading by end-CP5, but it looks like the rest of it has been deferred into CP6.
Resignalling is also critical, with Filton being done this August and the Badminton route next February, then Box, Bristol TM and Oxford.
 

Philip Phlopp

Established Member
Joined
31 May 2015
Messages
3,003
Bar the Auto Transformer stuff, indeed it does.

The ATF stuff is unimportant, the catenary is the important bit so it can be surveyed after sitting for a few days. It's currently expanding and contracting under tension, that will generally find any problems with droppers and the like, as well as confirming the auto tensioners are actually working correctly.
 

QueensCurve

Established Member
Joined
22 Dec 2014
Messages
2,195
The ATF stuff is unimportant, the catenary is the important bit so it can be surveyed after sitting for a few days. It's currently expanding and contracting under tension, that will generally find any problems with droppers and the like, as well as confirming the auto tensioners are actually working correctly.

Are the autotensioners based on springs rather than the traditional weights? If so, why is this seen as an advantage?
 

Domh245

Established Member
Joined
6 Apr 2013
Messages
8,426
Location
nowhere
Are the autotensioners based on springs rather than the traditional weights? If so, why is this seen as an advantage?

They are tensioned with tensorex units (so yes, spiral springs). The main advantages are their compact size and the fact that they can be installed above the lines rather than off to the side - which was one of the requirements of the series 1 OHLE.
 