A Mprthernm (Northern?)Client & Stakeholder manager has just come from a conference call regarding the situation re the routes in our area; the following are the main points by line of route. It is still too early to confirm the prospects for tomorrow morning, but some lines will clearly be inaccessible for a number of days:
· Barrow to Workington (the southern Cumbrian Coast): This is being walked now and has been inspected from the air; there is some confidence that this part of the line may be open in the morning. Network Rail has not been able to get signallers in today (this may also be an issue tomorrow), so we cannot run a proving service until the morning. It is clearly critical for the Sellafield workers and we will update as soon as we know more.
· Workington to Carlisle: This part of the line has suffered extensive damage and it will not be back in service for some time
· Lancaster Station: Power cuts in the town make the station unsafe to use currently, these are expected to remain until the first part of the week, so it is unlikely that we will be in a position to call.
· Lancaster to Barrow: Given the situation at Lancaster, we are exploring the possibility of using Morecambe as an alternative. The line however will not be proved until first thing in the morning, therefore we cannot confirm the service that will be in operation.
· Skipton to Lancaster/Morecambe: As said earlier a proving train is currently underway from Carnforth to Hellifield which will then reverse and travel to Carlisle via the Settle and Carlisle Line, once this has occurred a decision will be taken regarding tomorrows possible services.
· Skipton to Carlisle: See above
· West Coast Main line North of Preston: DRS are sending a proving train on this route, no information yet regarding the findings
· Hexham to Carlisle: The route proving train reported track bed slippage between Haydon Bridge and Bardon Mill. This has curtailed the route proving for this evening. Network Rail Control is now waiting for staff on site to advise them of the likely timescale to clear the debris. At the same time the Western Zone have been requested to attempt the route proving from the west to see if other obstructions lay between Haydon Bridge and Carlisle. Therefore the line is closed west of Hexham until further notice.
Even if the lines are returned to use, there are clearly several issues that will affect our ability to run a service, not least getting our people in to work over flooded roads, and after days of line blockages getting our rolling stock to the correct place to start its journey.
Therefore customers are advised to check before they leave home, up to date information can be sourced via real time journey updates on mobile by visiting www.journeycheck.com/northernrail or by Tweeting our team@northernrailorg
Those customers who hold tickets dated for this weekend may use them on any day until Monday December the 14th 2015.
To be fair to the railway (as I have been quite critical of some aspects on other threads) this is an impressively quick turnaround to returning services.
What about Carlisle-Dumfries? Is that, like Carlisle to Workington, out for the count at the moment?
The flood water North of Carlisle has dropped faster than predicted, therefore we are hopeful to have the line reopened by 1200. There will be some delays as a 20mph speed restriction has been put in place for quarter of a mile.
This is impressive and should deal a hefty blow to those who slag NR for anything and everything!
I think on this ne it was Virgin who were being slagged off for poor information and lack of buses.
According to the Realtime map for the Carlisle area,9M54 & 1M11 are the first 2 trains to / from Scotland since the line closed...
9M54 has just made it into Carlisle 55 mins late
That was certainly the aim of my criticism, all of which was levelled at VT; I have no criticism (indeed, rather I have compliments) for Network Rail. The failings were primarily customer service-related rather than operational (in a railway sense) or infrastructural.
Just to check, you have emailed VT with a conscience (but hopefully dispassionate) summary of your points about their management which you've also expressed in posts about them on here? I'm surethere's no point going on about it behind their backs.
So instead of speaking with the people who could actually do something about it, you've flooded this forum with countless rants about how things could be done better. Good job, way to achieve nothing!No, because I don't have time to waste on them failing to read it and sending me a pile of RTVs instead, which I have already claimed anyway.
So instead of speaking with the people who could actually do something about it, you've flooded this forum with countless rants about how things could be done better. Good job, way to achieve nothing!![]()
Of course it was. They were neither the people, nor was it the time/place to implement policy.I did speak with the station staff at the time (politely) with a couple of suggestions (proper ones, not what they could do with their lack of service), but it was too fraught for them to be taken on board.
Which is why the only choices that make any sense are either put up enough of a fuss to make them change or shut up.Companies are terrible at this generally, particularly large ones. They chuck out compensation because it's cheaper, and hope people will go away, which they generally do, but the problem remains unsolved.
Of course, it could be the case that people inside the company are just as able to spot the ridiculous as those of us on the outside.Edit: TBH, given that we know TOC management reads here, it's if anything as likely to get through posted on here as it is sent to Customer Services. The Routeing Guide thread (where they change something, we point out the unintended consequences, and they get fixed suspiciously quickly) is evidence enough of that.