HS2/3 and Transpennine Electrification

Status
Not open for further replies.

modernrail

Established Member
Joined
26 Jul 2015
Messages
1,440
Now that transpennine electrification has been delayed is it time to take stock and look at a slightly different way of achieving a high speed network?

I realise what follows is a long post, but I think this is an important debate that needs to be had now.

The current HS2 Y provides an imperfect solution for both Sheffield and the East Midlands, with stations outside the centre. Add a 20 min transfer from this place, plus the inconvenience of a change, and you have a less than satisfactory solution.

Transpennine electrification still leaves you with a relatively slow route and without the grade separation of a new line. Many of the current problems are caused by resilience issues not lack of electrification. Yes there is some interplay. However, arguably more urgent than electrification through the core are passing loops, 4 track sections and better signalling with shorter headways, and critically, longer trains.

I question the decision to put 5 transpennine an hour through the core rather than 4 longer trains because of the lack of resilience which seems to result in almost daily problems.

Longer term, a new trans-pennine line is the real solution, but electrification of the current line plus the expense of an imperfect Leeds limb of the Y make this investment harder to fund.

Would it be better to switch to a new HS2 solution, as follows, to provide tangible improvements quickly and huge improvements over time:

Change 1: the long term solution- Change the route of HS2 and deliver a better solution for the East Midlands using an existing but upgraded route which retains trains which make it to the city centres.

1a. Switch the Y so that the Leeds branch comes off at Manchester airport and across to a delta junction near Barnsley to Leeds and Sheffield. This also provides a new transpennine line (HS3) for the transpennine core, to both Leeds and Sheffield.

The Government would need to commit to starting the HS2/3 section at the same time as phase 1 of HS2 to ensure it is believed.

Sheffield trains could run on classic lines into the existing station, getting rid of the Meadowhall problem. Leeds trains would be high speed into Leeds and to an East Coast connection.

This would also provide a section of track that would provide very fast Leeds to Sheffield services and would offer the opportunity to speed up all cross country services that run via Sheffield, although in time some would run via Manchester instead (for instance a new Newcastle - York - Leeds - Manchester Airport - Crewe - Birmingham service)

1b. At the same time, or even sooner, deliver a substantial package of improvements, including electrification, to speed up and add capacity to the Midland Mainline, with savings of at least 30 mins on the Nottingham to London time. This would arguably be better for Nottingham, Derby and Leicester than being served by HS2 by a parkway station at Totton. I travel this route regularly and would much rather have a train that is a bit slower but direct. The Midland Main Line has less capacity issues that the East Coast or West Coast which makes this a serious proposition.


1c. Compensate Leeds for a slightly slower HS2 time to London by funding a series of more local improvements, such as electrification of the Harrogate line, meaningful tram-train lines (for instance to the airport), capacity improvements for the Aire Valley, series of city train stations (for instance Quarry Hill/Marsh Lane and Armley) and a much improved city system (whether the now proposed trolleybus scheme or a tram system or both). The total benefits of this package plus a high speed transpennine solution (including a fast connection to the north's main airport which is far more useful to cross Northern trains than it is to London bound trains ) might easily outweigh losing a little bit on the London journey time. These improvements could be funded now to speed up overall benefits to Leeds and Yorkshire, providing some jam much earlier than HS2 or HS3.

1d there is another possible change, to link Manchester to Liverpool by a similarly high speed line, or hugely upgraded Manchester to Liverpool via Newton le Willows or via Warrington area. London to Liverpool trains could leave the HS2 West Coast connector to join this line at or near Warrington (depending upon which line you connect to). It would be interesting to see what the journey time would be on this line v the journey via Runcorn. Might not be worth it but if it is quicker - would solve the Liverpool problem. Also, if you go via the Warrington Central route you could build a small loop and a stop at Liverpool Airport.

The stopping pattern of the high speed transpennine line could therefore be:

Northern: Liverpool - Liverpool Airport - Manchester Airport - Leeds - York - Newcastle

Southern: Liverpool - Liverpool Airport - Manchester - Manchester Airport - Sheffield

Scarborough, Middlesborough, Sunderland, Darlington, Dewsbury, Huddersfield, Stalybridge, Warrington etc would all be served by semi-fast inter-regionals that cater well for their commuter traffic. Some more changes might be required into the high speed network (but not in all cases by any means) at principal stations but the overall journey times would be quicker as a result and the trains would have more space for commuters with long distance passengers switching to the high speed network. These intermediate stations in the core would continue to benefit from the improvements made in 2 below.


Change 2 - Bring forward an immediate package of improvements for the existing transpennine core line, aimed at improving resilience and immediately increase capacity, including:

- signalling improvements to reduce headways;
- passing loops, so that existing local trains do not slow trains down and to provide capacity for additional local services that have been pushed out by transpennine. Particularly immediately east of Leeds Station, between Cooper Bridge and Huddersfield, and some facilities between Standedge and Manchester Victoria)
- projects to improve line speeds and therefore journey times, particularly for the post-northern hub route (fast Liverpool to Victoria and then to Stalybridge);
- find or fund additional rolling stock for immediate deployment, for instance:
/ make sure everything that can be electric on the west side is, for instance Blackpool to Manchester Airport, even if using cascaded stock from elsewhere;
/ find some trains to loco haul for Liverpool to Newcastle and Liverpool to Scarborough express services, for instance the old Gatwick Express trains
/ place an order now for Hitachi 7 coach bi-modes to replace the above diesel loco hailed as soon as possible. They would be able to run at full speed on the East Coast section, and under the wires to Leeds (with a short electrification from the East Coast line to Neville Hill), then diesel to Stalybridge, then electric to Liverpool. Also order to include purely electric hitachi trains for Manchester to Scotland transpennine route. Existing 350s cascaded onto NW electric routes (for instance Manchester Airport to Blackpool).

A cascade and new rolling stock order plan as follows:

- An acknowledgement that Northern is taking one for the national team by having to run a wide range of often old stock rather than uniform fleets as at Southern, London Overground, East Coast, West Coast etc and so ensuring maintenance is properly funded until we get to a uniform fleet and younger age, i.e. acknowledging that running old diesels and different train types is expensive and this is not the fault of the fare paying passenger - it is the Government that has imposed this position to suit its cascade plans.

- Spare 185's from above plan to form min 6 coach trains on most transpennine services (and all peak services).

- IF and only if Vivarail concept is proven, it is applied strategically on a few lines to release stock to other routes:
/ Windermere branch (yes it will mean a change at Oxenholme, but you could have a more regular service as well)
/ Whitby line
/ Leeds to Horsforth shuttle (which I don't think goes above 60) (but you would have to be super confident of it not breaking down on Leeds approaches)
/ possibly, but only possibly, the Huddersfield to Sheffield line. Arguably like speeds need improving on this line to above 60.
/ some of the Castleford/Knottingley routes, pending transfer to tram train operation, but again need to be super confident of it not breaking down across Leeds approaches.
- any others?

- new diesels in franchise requirement to go to inter-regional services that will not realistically be electrified until battery or bi-mode technology is so good that will be the solution but where 185 type door arrangement is good for quicker loading (eg York to Blackpool, probably Caldervale, Southport to Manchester etc) with refurbished 150's etc to metro and local services. 3 or 4 coach trains the norm on most routes. Very few 2 carriage trains.

- 158s see out the rest of their life on routes into East Midlands (Leeds -Nottingham) and quieter express routes (Leeds - Carlisle, Newcastle - Carlisle). 158s plus the new diesel stock become the inter-regional stock.

- pacers retired by 2020.

- a few routes switch to tram train by 2020, especially on Yorkshire side (Harrogate line branch to Leeds Airport, Castleford/Knottingley services, etc). New tram-train stock. Displaced stock goes to strengthen remaining heavy rail local services. New electric stock for Harrogate line.

- order placed fairly soon to replace all 150's and similar by 2022 they will be 40 years old then and so well ready for replacement even after mid-life extensions, especially as steel bodied) and 319s by 2025. Whether replacements are electric of further diesels will depend upon new service patterns with opening of Northern Hub. Hopefully, some diesels can be replaced with electrics. All capable of metro services (high capacity, 185 style door configuration). The lack of metro style diesel stock with this door arrangement is a real pain at the moment and definitely increases dwell times, but this plan would solve that problem reasonably quickly.

- order placed for new electric transpennine stock to meet opening of new HS2 Leeds to Manchester limb. 185s go to replace 158's. By 2030 they will be 40 years old, with a decent overhaul they should make that.

This is not to say that I don't think electrification of the core transpennine route is not important, but with limited resources, is this a better way of delivering the actual improvements required in the right order and getting some improvements funded now? If you change the Y you might actually release enough funds to crack on with electrification anyway but that is down to numbers I suspect and needs to be worked out.

I am less interested in exact numbers of units required for this plan than thoughts on the plan itself as a strategic solution to getting the most out of the investment money available.

I think this plan gives both a mostly electrified metro service for each of Liverpool (already well served), Manchester and Leeds, an electrified core high speed transpennine route, with good airport access and a sensible rolling stock strategy to 2030. It also provides a better London solution for Sheffield and the East Midlands.

I have not covered freight opportunities here, but I do like the Chunnel style suggestions to take lorries off the M62 and and into Chunnel style lorry carriers and would hope the above could incorporate this idea.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

johnnychips

Established Member
Joined
19 Nov 2011
Messages
3,822
Location
Leeds
A lot of interesting ideas, but can I just comment on one thing. A new line across the Pennines would probably cross the Peak District national park, and this would raise mass objections and demands for public enquiries.

The long-planned bypass of Mottram, Hollingworth and Tintwistle from the end of the M67 to the A628 had about one mile or less in the NP and this seemed to raise the planning bureaucracy to new levels. Proposals have, I think, been curtailed so it just avoids Mottram and thus the NP problem. Ironically, one objection to it proposed reopening the Woodhead line and putting lorries on a shuttle at Hattersley and taking them off at Silkstone. This was sensibly rejected. Do not underestimate the power of the countryside lobby.
 
Last edited:

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,589
Location
Nottingham
A lot of interesting ideas, but can I just comment on one thing. A new line across the Pennines would probably cross the Peak District national park, and this would raise mass objections and demands for public enquiries.

A straight line from Manchester to Leeds approximately follows the A62 and passes well to the north of the National Park. However any Manchester-Sheffield route would pass through it.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
The long-planned bypass of Mottram, Hollingworth and Tintwistle from the end of the M67 to the A628 had about one mile or less in the NP and this seemed to raise the planning bureaucracy to new levels. Proposals have, I think, been curtailed so it just avoids Mottram and thus the NP problem.

A feasibility study for road tunnel was promised in December and it was reported a few days ago that a contract has been awarded:

http://www.constructionenquirer.com/2015/07/22/feasibility-study-into-trans-pennine-tunnel-plan/

A £1.3m contract has been handed to a joint Mouchel/Hyder team to study whether a Trans-Pennine tunnel, costing billions, helping to link Sheffield and Manchester would be viable.

This strategic study is one of several looking at solutions to tackle congestion and stimulate economic growth that have been commissioned by the Department for Transport and Transport for the North.

It will investigate the strategic and economic case for a new high-standard highway route between Manchester and Sheffield, including assessing the potential of combining with a rail or light rail link.

It is anticipated that the new route will cross the Pennines and the Peak District National Park by means of a road tunnel extending for several miles.

Road Minister Andrew Jones said: “As part of our long-term economic plan we are investing a record £13bn in transport for the North and North-East.

“Today’s announcement will look at building stronger links between Manchester and Sheffield, meaning more jobs and opportunities for people across the region.”

http://eandt.theiet.org/news/2015/jul/transpennine-tunnel-study.cfm

Government officials are assessing the possibility of a road tunnel under the Pennines to help fill a significant gap in England's strategic road network.

The Department for Transport (DfT) and Transport for the North (TfN) have commissioned a strategic study into on the viability of a Trans-Pennine Tunnel as identified in the Roads Investment Strategy published in December 2014.

A £1.3m contract has been awarded to a Mouchel/Hyder joint venture for professional services to assist Highways England with the study, which is one of a number being carried out to identify solutions to congestion problems and support economic growth.

The study will investigate the strategic and economic case for a new high-standard highway route between Manchester and Sheffield, including assessing the potential opportunities of combining with a rail or light rail link. It is expected that the new route will cross the Pennines and the Peak District National Park by means of a road tunnel several miles long.


Road Minister Andrew Jones said: "Today’s announcement will look at building stronger links between Manchester and Sheffield, meaning more jobs and opportunities for people across the region."


The Roads Investment Strategy highlighted a connectivity gap between Sheffield and Manchester, pointing out that the direct route between the two cities is 35 miles long but traffic on the M62 motorway - the only high-performance trans-Pennine route - must travel more than 65 miles.


Dr Jon Lamonte, lead officer for Transport for the North, commented: "We welcome this important milestone and look forward to the commencement of the study which is a key element of both the RIS 1 programme and Transport for the North’s longer-term transport strategy as set out in March 2015. We look forward to continued working with Highways England and the Department for Transport to deliver the vision for a Northern Powerhouse.
 

johnnychips

Established Member
Joined
19 Nov 2011
Messages
3,822
Location
Leeds
Am I reading this wrong, but has £1.3M been promised for a study. If so .....
--- old post above --- --- new post below ---
Sorry, just got my breath back. The obvious route is from the end of the M67 at Hattersley if you want to have a more direct route, which is implied. The three villages after that will have to be bypassed. All the planning for this has already been done; it has not taken place because of objections that it impinges into the Peak District National Park and the financial crisis. And suddenly a vague tunnel 'several miles long' in an unknown location appears and will benefit some company by over a million just to look at it. You can't have a tunnel from Mottram(M67) to Dodsworth(M1)!

I am sorry if this is off thread, and do move it into 'other transport' if you want, but it just shows how much fun is going to happen if a new HS3 trans-pennine line is going to take place.
 
Last edited:

NotATrainspott

Established Member
Joined
2 Feb 2013
Messages
3,304
Now that transpennine electrification has been delayed is it time to take stock and look at a slightly different way of achieving a high speed network?

...

Modernrail, welcome to the forum. You've definitely thought through your idea but HS2 Ltd were asked to look at three basic high speed route networks - the Inverted A, the Reverse S and the Reverse E - back when the initial plans for the network were being developed and they decided that it would be best to build the network that is planned today, despite it requiring the most track to be built. The planned Y network is the core of the 'Inverted A' option, whereby the HS2 main line runs from London to Lanarkshire, with spurs for Birmingham, Manchester and Liverpool, plus an eastern branch running from Birmingham to Newcastle via the East Midlands, South Yorkshire and with a branch to Leeds. The link between Manchester and Leeds was then to be provided by a classic route upgraded to 140mph standards.

The Treasury can effectively fund any scale of investment if there is a clear case for doing so, so the total price tag of HS2 isn't really important. What matters is that the money spent is spent wisely, and from their initial analysis the benefits of running the main line across the Pennines, either to Manchester from Yorkshire or vice-versa, are outweighed by the disbenefits. The case for the eastern arm of HS2 Phase 2 is that the Phase 1 line will have capacity left over after serving all of the current WCML destinations, and the existing MML and ECML tracks won't have any capacity left. Putting long distance passengers from the MML and ECML onto HS2 then makes best use of not only the expensive HS2 infrastructure south of Birmingham but also relieves the classic mainlines so that they can be better suited for the people living in Leicester, Peterborough and the like.

The scope for upgrading the MML and ECML further in lieu of HS2 is limited without needing to spend many billions on massive reconstruction works which would take years to complete. The ECML is seeing massive improvements as part of the Thameslink and InterCity Express programmes, including power supply upgrades and the installation of the same sort of in-cab signalling that will be used on HS2. Even without electrification, the MML will see improvements in the form of track realignment around Market Harborough and other areas to increase linespeeds. The improvements reasonably practical to implement on both lines will make it possible to carry the ever-increasing numbers of passengers on the railways up to a point, but the only long-term solution after that point is for them to use a new line.

It's also important to remember that the timescales involved in HS2 are significantly longer than are the case for the sorts of improvements you would implement. HS2 Phase 2 will take 15 years to complete, but smaller projects like electrifying the local lines around Leeds, Sheffield and the East Midlands could be complete almost half a decade earlier. Changing the plans for HS2 would not make it feasible to deliver these improvements any faster or cheaper, since the skill sets and budgets involved are separate.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,589
Location
Nottingham
Modernrail, welcome to the forum. You've definitely thought through your idea but HS2 Ltd were asked to look at three basic high speed route networks - the Inverted A, the Reverse S and the Reverse E - back when the initial plans for the network were being developed and they decided that it would be best to build the network that is planned today, despite it requiring the most track to be built. The planned Y network is the core of the 'Inverted A' option, whereby the HS2 main line runs from London to Lanarkshire, with spurs for Birmingham, Manchester and Liverpool, plus an eastern branch running from Birmingham to Newcastle via the East Midlands, South Yorkshire and with a branch to Leeds. The link between Manchester and Leeds was then to be provided by a classic route upgraded to 140mph standards.

Largely agree with that except that "Lanarkshire" should be "Lancashire" I think.

However there is one slight reservation, that I don't think the HS2 studies that produced the Y network took much account of the possibilities of capturing extra traffic across the Pennines. If the Northern Powerhouse is anything like it is being talked up to be then the "agglomeration effect" would increase this demand above what a simple extrapolation of the existing demand would suggest. It is possible, though I think unlikely, that taking account of this factor would swing the balance in favour of the north-east being served via Manchester instead of by a route through the East Midlands.

However it is also worth noting that York and point north along the ECML will only be about 35min quicker from London via HS2 than the existing ECML timings, and the various proposals for faster ECML service will erode this difference further. It is possible therefore that trains from London to Leeds (or beyond) would be no quicker via HS2 through Manchester and across the Pennines than via the ECML through Doncaster.
 

NotATrainspott

Established Member
Joined
2 Feb 2013
Messages
3,304
Largely agree with that except that "Lanarkshire" should be "Lancashire" I think.

However there is one slight reservation, that I don't think the HS2 studies that produced the Y network took much account of the possibilities of capturing extra traffic across the Pennines. If the Northern Powerhouse is anything like it is being talked up to be then the "agglomeration effect" would increase this demand above what a simple extrapolation of the existing demand would suggest. It is possible, though I think unlikely, that taking account of this factor would swing the balance in favour of the north-east being served via Manchester instead of by a route through the East Midlands.

However it is also worth noting that York and point north along the ECML will only be about 35min quicker from London via HS2 than the existing ECML timings, and the various proposals for faster ECML service will erode this difference further. It is possible therefore that trains from London to Leeds (or beyond) would be no quicker via HS2 through Manchester and across the Pennines than via the ECML through Doncaster.

No, I meant Lanarkshire. That's what the original Inverted A plan had, even if the Y network as planned today doesn't go as far as that.

My point about the fact that the Treasury can basically spend any amount of money it wants is that if there is a business case for TransPennine improvements, then it is not an absolute necessity to piggyback the provision of this onto the infrastructure needed for Phase 2. It's more important to ensure any infrastructure built is fully suited to the role it needs to play, and running Yorkshire/North East services via Manchester doesn't really do that. For one, it means you can't properly serve the East Midlands at all, and even if it might still be within the realms of possibility that the MML could compete on Derby/Nottingham to London flows it's not the case that it could compete running the other way, from the East Midlands to Leeds, York and the North East. The best way of serving the places east of the Pennines is to have a north-south oriented line link them up and connect to Phase 1 east of Birmingham.
 