Whilst I acknowledge, I'm about 20 years early on this one, reports today in RTM about a £30m fund to push feasibility stage plans forward for the Northern Powerhouse, led me pondering exactly what we might end up with as a service pattern and how that might impact on the current HS2 Ph2 Plans.
Using the options in this news item...
http://www.railtechnologymagazine.c...d-plans-to-transform-rail-in-the-north/101306
Option 2 alone is £12-19Bn
Options 3 & 7 would be £9.5-15Bn
Option 7 & 8 would be £7.5-12Bn
Option 2 clearly (in my head) uses a branch from HS2 near Barnsley and a "Woodhead" route, where as Options 3 & 7 or 7 & 8 aren't as obviously linked to HS2.
Assuming current service patterns on the Leeds to Sheffield HS2 line 10 paths are used by HS2 services, leaving potentially 8 paths available (using Birmingham Interchange as an indication of maximum paths).
Given the speed differentials, the likelihood that a 15 minute frequency will be part of the aspiration for Leeds-Manchester, plus the idea being thrown about have regional HS commuter units on the Leeds to Sheffield link** I'm starting to think that the Leeds-Sheffield link will be looking very well used from day one and that 4 platforms at Meadowhall and 5 at Leeds just isn't going to meet the needs from day one, especially so with the current terminus style station at Leeds.
**This could be an alternative to the semi-fasts and/or the XC services.
Discuss ?
Using the options in this news item...
http://www.railtechnologymagazine.c...d-plans-to-transform-rail-in-the-north/101306
Option 2 alone is £12-19Bn
Options 3 & 7 would be £9.5-15Bn
Option 7 & 8 would be £7.5-12Bn
Option 2 clearly (in my head) uses a branch from HS2 near Barnsley and a "Woodhead" route, where as Options 3 & 7 or 7 & 8 aren't as obviously linked to HS2.
Assuming current service patterns on the Leeds to Sheffield HS2 line 10 paths are used by HS2 services, leaving potentially 8 paths available (using Birmingham Interchange as an indication of maximum paths).
Given the speed differentials, the likelihood that a 15 minute frequency will be part of the aspiration for Leeds-Manchester, plus the idea being thrown about have regional HS commuter units on the Leeds to Sheffield link** I'm starting to think that the Leeds-Sheffield link will be looking very well used from day one and that 4 platforms at Meadowhall and 5 at Leeds just isn't going to meet the needs from day one, especially so with the current terminus style station at Leeds.
**This could be an alternative to the semi-fasts and/or the XC services.
Discuss ?