Tokens are not cheap, at least not anymore. You've still got conventional point machines with conventional train detection at a passing loop because the old train operated loop points are no longer available. And then you need TPWS equipment with your stop boards, and indicator lights to show TPWS is working, which, along with your points indicators, might as well be signals). You need power for all this and a good secure cable route between the token machines at either end of the section for the circuits. On top of that the machines themselves are probably now completely alien to local S&T maintenance staff who otherwise are trained to deal all modern equipment. Skills, Spares, Extra Training, Token balancing, etc . . .

http://www.vmslimited.co.uk/cls.htm

Axle counter based TCB with the simple lightweight colour light signals from (for instance) VMS would be far more suitable for such a minor low-speed route. As an LED this signal is very reliable and low maintenance, and for the extremely rare occasions you do need to access the head, you take a possession and fold the unit down to work at ground level rather than the structure requiring modern safety access ladders to fully fenced high-level platforms so you can work up there. Those traditional measures increase the size and weight of conventional structures significantly and increase the size and cost of their foundations.

It's no wonder railway costs are so ludicrous then. What's wrong with a simple physical token for each section based at Bricket Wood (and if you collect it from BW, run to the terminus and back to return it, it's self-balancing) and if the sprung points are unavailable (why on earth though?), then surely it is not beyond the wit of man to have a mechanical system of some sort (i.e. similar to that used to operate the level crossing) that automatically sets and resets the points after the train passes over them? ...and why would you need a token machine at St Albans? Trains wouldn't magically spring into existence there - they would have come from Bricket Wood and thus already be in possession of the token for that section. In fact, by the same measure if the last train of the day leaves the token for Watford to BW at Watford overnight the first train can pick it up and run it to BW, and you don't need one at Watford either, eliminating the need for all the cabling.

You don't need full-on train detection, just simple common-sense rules - you can operate in the block you have the token for in either direction, and you don't proceed into the other block section unless you hold the token for it! If you are that mentally challenged that you're confused about if you physically have the token in your hand then just ring the signaller whilst you're sitting at Bricket Wood, they're nice people who should be able to get you the special help you need. The railway doesn't exist in a parallel dimension, cut off from reality, though it really seems to act like it sometimes.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

MarkyT

Established Member
Joined
20 May 2012
Messages
7,549
Location
Torbay
It's no wonder railway costs are so ludicrous then. What's wrong with a simple physical token for each section based at Bricket Wood (and if you collect it from BW, run to the terminus and back to return it, it's self-balancing) and if the sprung points are unavailable (why on earth though?), then surely it is not beyond the wit of man to have a mechanical system of some sort (i.e. similar to that used to operate the level crossing) that automatically sets and resets the points after the train passes over them? ...and why would you need a token machine at St Albans? Trains wouldn't magically spring into existence there - they would have come from Bricket Wood and thus already be in possession of the token for that section. In fact, by the same measure if the last train of the day leaves the token for Watford to BW at Watford overnight the first train can pick it up and run it to BW, and you don't need one at Watford either, eliminating the need for all the cabling.

You don't need full-on train detection, just simple common-sense rules - you can operate in the block you have the token for in either direction, and you don't proceed into the other block section unless you hold the token for it! If you are that mentally challenged that you're confused about if you physically have the token in your hand then just ring the signaller whilst you're sitting at Bricket Wood, they're nice people who should be able to get you the special help you need. The railway doesn't exist in a parallel dimension, cut off from reality, though it really seems to act like it sometimes.

Leaving aside the points for a moment.

At its simplest the line could be run with two train-staffs equipped with different annets key configurations kept in and passed through their respective key release instruments at Bricket Wood for each movement. These would need to be in a locked hut at this unmanned station. Signals or stop boards protecting single lines must have TPWS, so the stop boards here will need trainstop loops controlled by withdrawing the appropriate key, and with the appropriate indicators to confirm the loops inactive. See this example at Tenby (A NSTR remote loop). https://www.flickr.com/photos/kevin_r_boyd/11674413745

The problem with this arrangement is what happens when one train leaves the branch by the main line connection at Watford. Unless the staff was returned by road to Bricket Wood, the second train would remain stuck at the far end of the line. The conventional way to resolve that would be to keep the staff working at the far end of the branch (hence no equipment at St Albans), but use a key token system with machines at both ends for Watford - Bricket Wood. Now the token held by the train going mainline can be put back into the machine at Watford, and another would become available for the section at Bricket Wood. That needs a cable route, as would the operational telephones at the passing point.

In simple form, a token or staff system cannot support a Penryn style loop, as one platform is in one of the single line sections. A small signalling overlay could allow it however in conjunction with staff or token, but we're still talking a little local train detection and a few signals.

Returning to the points, the original hydropneumatic train operated mechanism was a long time in development and required a lot of testing and paperwork by expensive boffins and consultants to convince safety authorities that, without a conventional facing point lock (FPL), it was sufficiently safe and secure. A FPL is normally an absolute requirement for passenger operations. The train operated mechanism was always limited to a maximum speed in either direction of 15MPH nonetheless. All the train operated points in South Wales, including Tenby in the photo linked above and the Central Wales line, have now been replaced by motor worked points (I checked the sectional appendix: there's a note to the effect for every loop). Whether train operated or motor operated a set of points needs an indicator in the facing direction, and with motor operation an indicator in the trailing direction too, which can be combined with the stop board TPWS indicator. All these indicators are starting to look like so many colour light signals, and with the motor operated points requiring some local train detection to make sure they're clear of trains before moving it's all starting to look a lot like a fully signalled layout.

There are other simple point mechanisms available from European manufacturers used for light rail and tramways, but as far as I know nothing currently approved for UK heavy rail passenger use. If a project such as Watford - St. Albans wished to use such a new product they would have to take on the cost and risk of getting that approval (with all the expensive boffins and consultants involved).

TCB using axle counters only requires one rail mounted inductive sensor head unit at each end of the single line regardless of the length of the section between, so full train detection is no longer so equipment and power intensive as it was with track circuits which are length limited to typically around 1km. Yes communications cables are required between the two ends of a counter section, requiring a cable route, but you'd need a cable route for a token circuit and telephones too.

I think token or staff working to modern standards would offer no real savings over a modern lightweight modular signalling installation, yet would slow down the passing loop operation and require drivers to leave the cab whilst exchanging keys. Even a token and staff system would have to be supervised and controlled by a signaller somewhere, so if added to the WCML workstations it would still require a change to the screens and controls.

Here's a useful page on the subject: http://www.railsigns.uk/photos/p_points1/p_points1.html
 
Last edited:

Trog

Established Member
Joined
30 Oct 2009
Messages
1,546
Location
In Retirement.
Out of interest, does the passing loop have to be at Bricket Wood? Presumably, to make a half-hourly timetable work, the only requirement is that neither end of the line should be more than 11-12 mins from the loop? It looks from Google maps like there's plenty of countryside between Garston and Bricket Wood, where buying land would presumably be cheaper (and less distance to lay the cables). And that would mean no platform extensions required. I'm guessing though that the other side to that is that a passing loop not in a station might need to be longer to keep the timetable robust.

Even more countryside north of Bricket Wood, but that obviously would mean further to lay the cables.

There was once a loop and second platform at Bricket Wood so the land should already be there ready to use.
 

AM9

Veteran Member
Joined
13 May 2014
Messages
16,007
Location
St Albans
There was once a loop and second platform at Bricket Wood so the land should already be there ready to use.

The land is still there but it has been populated by trees. It would be practical to take some of them down to reinstate the loop though, without upsetting too many of the residents, especially when they realise that their house prices might rise a bit as a result of better services! That's why a Penrhyn layout would be better than a second platform or moving the current track to make an island platform.
Aparently, the station was quite large in the '20s. Here is a link to an article where a picture of the station in its heyday can be seen:

http://www.abbeyline.org.uk/routehistory.htm

The picture is looking north so the land on which the signal box and platform stood is not availble for rail use now, but the platforms were long enough for 9-coach trains so the loop must have been at least 250m long.
 

jon0844

Veteran Member
Joined
1 Feb 2009
Messages
30,836
Location
UK
House prices would almost definitely rise if the rail line became more useful, so I think it would be mad for anyone to be against any form of upgrade.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,581
House prices would almost definitely rise if the rail line became more useful, so I think it would be mad for anyone to be against any form of upgrade.

Except for those immediately adjacent to the line, the occupants of which you need the most help from, such as potentially buying parts of back gardens.
 

mr_jrt

Established Member
Joined
30 May 2011
Messages
1,574
Location
Brighton
Regardless of everything else, just wanted to thank you for taking the time to provide such a detailed and thoughtful reply (as usual), MarkyT. :)
 
Status
Not open for further replies.

Top