At Redhill, the up side loop (non-electrified) has a sign fixed to a sleeper saying "DB Schenker Track Maintenance" with an arrow pointing along the loop. I was unaware that any UK main line (albeit infrequently used in this case) track was maintained by anyone other than Network Rail - are there many other examples of this, and with other operators?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,757
Anything that is leased tends to be dealt with by the operator (or not as the case can be...)
 

ChiefPlanner

Established Member
Joined
6 Sep 2011
Messages
8,355
Location
Herts
Or the siding leasor or operator - say the Felixstowe Dock and Railway Company - or a power utility company - used to be termed "red sidings" .....
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,322
I think the Isle of Wright is maintained by Island Line.
Only for day to day inspections and routine stuff I think; when it goes seriously wrong, like the recent landslip, repairs seem to be down to NR. It is them being quoted in press reports about the completion.
 

High Dyke

Established Member
Joined
1 Jan 2013
Messages
5,029
Location
Yellabelly Country
Only for day to day inspections and routine stuff I think; when it goes seriously wrong, like the recent landslip, repairs seem to be down to NR. It is them being quoted in press reports about the completion.
No doubt it's them that is also picking up the repair bill...?
 

tsr

Established Member
Joined
15 Nov 2011
Messages
7,400
Location
Between the parallel lines
Following Operation Mountfield, where NR took over control and responsibility for many local yards and freight lines (including, I believe, Salfords and Ardingly), Redhill Up Goods Loop (in part), Snowplough Siding and Up Yard are now some of the few sections of track in the area still operated and maintained by DBS.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,776
Location
Nottingham
No doubt it's them that is also picking up the repair bill...?

Probably so. Otherwise Island Line would have to carry insurance for the very rare but very serious events like this, which would be disproportionately costly for a small operator. The cost of fixing the odd landslide is much less of an issue for an organisation the size of Network Rail. I don't know what insurance they carry, but if they do the "excess" would be much greater than what someone like Island Line would need - and the premium therefore much lower pro rata.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,768
Location
Scotland
I don't know what insurance they carry, but if they do...
I suspect that, in common with many large infrastructure organisations, they self-insure. Any unforseen operational costs are paid out of the capital works budget. So if there are several major repair jobs, planned projects may be delayed or reduced in scope.
 

infobleep

On Moderation
Joined
27 Feb 2011
Messages
13,453
I suspect that, in common with many large infrastructure organisations, they self-insure. Any unforseen operational costs are paid out of the capital works budget. So if there are several major repair jobs, planned projects may be delayed or reduced in scope.

Reducing the scope of planned projects can't be easy given that the railways are evicting more popular, with more people travelling. Again delaying projects also can't be easy.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,768
Location
Scotland
Reducing the scope of planned projects can't be easy given that the railways are evicting more popular, with more people travelling. Again delaying projects also can't be easy.
I never said it would be easy. In some cases NR would be able to issue bonds or borrow to cover the shortfall but we've already seen projects pushed back or postponed.
 

steamybrian

Established Member
Joined
26 Nov 2010
Messages
2,004
Location
Kent
The Spa Valley Line between Birchden Jn and Eridge is maintained by rail contractors Keltbray under contract by Spa Valley Railway even though it is leased from NR.
 

adrock1976

Established Member
Joined
10 Dec 2013
Messages
4,450
Location
What's it called? It's called Cumbernauld
Would Highbury & Islington to both of the New Cross stations count?

I believe this section of the track (former Metropolitan Railway/LU East London Line) is owned by Transport for London, which also has the London Overground services running over it.

In peace

Adam
 

Chris125

Established Member
Joined
12 Nov 2009
Messages
3,272
Location
Isle of Wight
No doubt it's them that is also picking up the repair bill...?

The following describes the situation back in 2001, I imagine something similar still applies:

Island Line is responsible for the maintenance of the infrastructure
generally e.g. track, signalling, electrification equipment and buildings,
however Railtrack is responsible for the maintenance of structures,
earthworks and the formation below 450mm from the underside of the
sleepers. Railtrack is responsible for renewals except permanent way and
the non-structural elements of stations.

Chris
 

Deepgreen

Established Member
Joined
12 Jun 2013
Messages
7,491
Location
Gomshall, Surrey
Following Operation Mountfield, where NR took over control and responsibility for many local yards and freight lines (including, I believe, Salfords and Ardingly), Redhill Up Goods Loop (in part), Snowplough Siding and Up Yard are now some of the few sections of track in the area still operated and maintained by DBS.

Maybe that explains why I cannot get a straight answer out of NR about having the sodium floodlights over the Snowplough Siding switched off - they are on 24 hours a day, every day, and have been solidly for the nearly three years I have been commuting from Redhill, despite the siding never having been used to my knowledge in all that time! Southern said they were NR's responsibility, and NR said the reverse. Maybe they are DB's.
 

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,581
Airport junction and the branch line managed by baa or Heathrow airport holdings harrow on the hill to Amersham managed by LU.
 

Mojo

Forum Staff
Staff Member
Administrator
Joined
7 Aug 2005
Messages
21,200
Location
0035
Airport junction and the branch line managed by baa or Heathrow airport holdings harrow on the hill to Amersham managed by LU.
Plus the line from East Putney to Wimbledon is owned by LU but power supply and signalling is dealt with by Network Rail, as a legacy arrangement from when the line was owned by BR. There are infrequent SWT services which use this bit of track.

There was an interesting incident a few years ago where a District line Train Operator reported a rough ride and the P-Way guys went to check it out and found a defect that required a 10mph TSR to be implemented until it could be fixed overnight.

The TSR was signed using LUL-standard signs but the NR Signal Operator was apparently not happy to allow trains to run as he believed that NR-standard signage was required, however the NR guys would not attend to erect such signage as it was not their property.

From memory there was a fairly prolonged (by LU standards) shutdown. I cannot remember exactly how it was resolved, but I think in the end the Signal Operator stopped the trains and advised them of the speed restriction.
 