I guess the cardiff bay shuttle spends more time stationary than moving.
but surely the question was a "service" not the whole diagram (which would consist of multiple services)?I guess the cardiff bay shuttle spends more time stationary than moving.
but surely the question was a "service" not the whole diagram (which would consist of multiple services)?

But out of a total working timetable schedule of 198 minutes, it's only booked to sit for 34 minutes (as you say 24 of those at Leeds), so the proportion isn't that big, at 17%. Still infuriating when you're on it though, but any passengers for York can change onto TPE (and get to York at the time you'd otherwise only be at Cross Gates) if you're lucky with the connection.The last but one Blackpool-York of the day sits at Leeds for 24 minutes before proceding to York.

A similar ratio - 1P79, 19:53 Corby to St Pancras, has a total of 29' dwell in its 92' journey, most of it at Kettering.
My guess is shorter-distance services have pathing time - e.g. waiting for a single line section to clear, and longer-distance services have recovery time built in e.g. there's a lot of places that a London to Aberdeen or Penzance to Edinburgh service can get delayed.Why do trains have to have such long dwell times?
Slow, perhaps, but no excessive dwell.Sheffield to Huddersfield . It's such a painful journey especially after Penistone.
Indeed, after 1P64's gone, 1P69 has a long dwell to drop roughly into the next hourly path, and each subsequent Down arrival has both a long layover at Corby and a long dwell at Kettering to keep that pattern. I've never really looked into it enough to establish why the pattern through the rest of the day, with each Down arrival returning south after a minimum turnaround. Either way, 1P69's overall journey time is longer so the extended Kettering call is smaller as a proportion!Similarly the 16:36 Derby - St Pancras does pretty much the same thing, 23 mins at Kettering.
Sheffield to Huddersfield . It's such a painful journey especially after Penistone.
Why do trains have to have such long dwell times?
As a passenger, I would find it mighty annoying to travel from New Pudsey to York, and having to spend 24 minutes in Leeds on that service.
I'm guessing the whole journey without that would be less than an hour.
Why do trains have to have such long dwell times?
As a passenger, I would find it mighty annoying to travel from New Pudsey to York, and having to spend 24 minutes in Leeds on that service.
I'm guessing the whole journey without that would be less than an hour.
If we ignore a pretty much one off London Overground service, then this *might* be the top ranked by ratio...
Weekdays 19:35 Littlehampton to Bognor Regis. 29 Minutes duration, 15 minutes of which is parked up at Barnham, along with a mere 30 seconds at Ford. At 53.5%, it is scheduled to spend more time stopped than moving.
LITTLEHAMPTON 19:35:00
FORD 19:38:30 19:39:00
BARNHAM 19:43:00 19:58:00
BOGNOR REGIS 20:04:00
Sometimes these things do have an advantage though. The 16:36 Derby-St Pancras is very slow, but you can get some pretty good advance fares on it compared to other services around that time. The undesirability of travelling on it is obviously something of which EMT are very aware.