I understand this has been delayed for a third time now (or perhaps indefinately?) as the scheme should have been commissioned on 12th/13th April.

Is the only reason for the delay due to the LiDAR (and/or RADAR) not working properly at the level crossings or are there other reasons too.

Anyone know if the LC problems have been sorted at Billingshurst?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

RichardN

Member
Joined
29 Nov 2013
Messages
430
I understand this has been delayed for a third time now (or perhaps indefinately?) as the scheme should have been commissioned on 12th/13th April.

Is the only reason for the delay due to the LiDAR (and/or RADAR) not working properly at the level crossings or are there other reasons too.

Anyone know if the LC problems have been sorted at Billingshurst?

They were blaming late running on trains via Billingshurst tonight on problems with a level crossing, so I suspect not.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,577
No it's not specifically the LXs that are the problem. It's complicated though.
 

Tio Terry

Member
Joined
2 May 2014
Messages
1,197
Location
Spain
The principle reason for the job being put back is the contractors inability to get the Interlocking Data Preparation completed to the satisfaction of NR. This is due to a lack of competent Data Prep. Engineers.

Billingshurst Crossing renewal - complete with Lidar - is going ahead this weekend. There was a problem with the Local Control Module that has resulted in a modification being required, this will be implemented this weekend.
 

SussexMan

Member
Joined
23 Oct 2010
Messages
553
Doesn't seem to be a lot of activity at the moment. However, there are new (not yet commissioned) signals on both platforms at Polegate. Both are at the level crossing end. The one on the up line is a replacement for the existing semaphore. However it would appear that the one on the down platform might be for reverse running. It's hard to tell as the signal head is covered up but looks like it is facing the Eastbourne direction. If it was for normal direction running I assume you wouldn't put it immediately after a level crossing. Can anyone shed any light on the new signalling arrangements?

Does the new signalling mean that line capacity will be significantly increased as there appear to be quite a few additional signals along the line compared the the current situation.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,577
Does the new signalling mean that line capacity will be significantly increased as there appear to be quite a few additional signals along the line compared the the current situation.

Yes headways are coming down and Linespeeds going up in some sections.
 

Yabbadabba

Member
Joined
23 May 2014
Messages
385
NR won't commit a date for the East Sussex resignalling until their contractors can guarantee its reliability!

April 2015 was a date that I was given yesterday, if it can't make that then the whole project might be sidelined (mothballed) between 2 & 7 years! Getting beyond a joke now!

On a brighter note the Arun Valley inclucding the infamous OD crossing at Billingshurst seems to be settling down now.
 

carriageline

Established Member
Joined
11 Jan 2012
Messages
1,897
April 2015 was a date that I was given yesterday, if it can't make that then the whole project might be sidelined (mothballed) between 2 & 7 years! Getting beyond a joke now!



On a brighter note the Arun Valley inclucding the infamous OD crossing at Billingshurst seems to be settling down now.


What boxes control East Sussex? Not completly clued up with geography down there!


Sent from my iPhone using Tapatalk
 

Yabbadabba

Member
Joined
23 May 2014
Messages
385
What boxes control East Sussex? Not completly clued up with geography down there!


Sent from my iPhone using Tapatalk

East Sussex Coast re-signalling (stage 1) will see Bexhill Signal Box, Havensmouth Xing Box, Pevensey & Westham Signalbox, Hampden Park Signalbox, Eastbourne Signalbox, Polegate Signalbox, Berwick Signalbox and the up line at Glynde transferring from Lewes Signalbox to the new workstation.
--- old post above --- --- new post below ---
That might please one or two people I know :)

Now how about sprucing up the existing signalling - e.g. the signal posts could do with a lick of paint...

Now they are talking about October this year again as it seams the three new interlockings areas are now working successfully in shadow mode.
 