ECML ITT issued today 21 Mar 14

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

jopsuk

Veteran Member
Joined
13 May 2008
Messages
12,774
so no sign of the Cambridge (and Kings Lynn) fast services being taken over by the ECML franchise post 2018 (thameslink through running) then? Long been a rumoured idea. Doesn't kill off the idea of using IEP SET for those services, of course. But to me it would indicate the 365s are more likely to stay put.
 

Deerfold

Veteran Member
Joined
26 Nov 2009
Messages
13,718
Location
Yorkshire
so no sign of the Cambridge (and Kings Lynn) fast services being taken over by the ECML franchise post 2018 (thameslink through running) then? Long been a rumoured idea. Doesn't kill off the idea of using IEP SET for those services, of course. But to me it would indicate the 365s are more likely to stay put.

Aren't they supposed to be going through the Thameslink core?
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,275
AIUI the Thameslink service from Cambridge will be a semi-fast; the fast services from Kings Lynn and Cambridge will run to Kings Cross - there's a section in the TSGN Stakeholder brief that describes the Thameslink service and then adds:

4.102 These [the Thameslink trains above] will be in addition to the fast King’s Cross trains to and from Cambridge and King’s Lynn. Overall, this will provide an extra two trains per hour into central London off-peak.
https://www.gov.uk/government/uploa...a/file/245205/consultation-responses-tsgn.pdf
 

Deerfold

Veteran Member
Joined
26 Nov 2009
Messages
13,718
Location
Yorkshire
AIUI the Thameslink service from Cambridge will be a semi-fast; the fast services from Kings Lynn and Cambridge will run to Kings Cross - there's a section in the TSGN Stakeholder brief that describes the Thameslink service and then adds:

Thanks for that.
 

Stats

Member
Joined
27 Sep 2009
Messages
943
AIUI the Thameslink service from Cambridge will be a semi-fast; the fast services from Kings Lynn and Cambridge will run to Kings Cross - there's a section in the TSGN Stakeholder brief that describes the Thameslink service and then adds:
And confirmed in the ICEC ITT. There's a detailed section in box 5.2 on pages 53 and 54 on what TSGN services the ICEC TOC must allow for. Too long to quote it all, but the off-peak southbound pattern is
C) 8tph over Welwyn Viaduct southbound in each hour 1000 to 2159 (measured at King’s Cross or St Pancras). 
4tph (2 from each of Peterborough and Cambridge) run to and from the Thameslink core, running slow line to call at Stevenage but fast line from Woolmer Green Junction to Finsbury Park non-stop; 
2tph Cambridge Express to King’s Cross, running fast line, non-stop, from Hitchin to King’s Cross; and 
2tph Cambridge line to Thameslink core, running fast line only from Woolmer Green Junction to Digswell Junction (calling at Welwyn North).
 