Thanks. That begs a couple of other questions I'm now puzzled about.
Firstly, that implies the New Cross Gate line (which already plays host to the new-ish overground services) is going to see a lot of new Thameslink services (ie. all the new ones through London Bridge). Does it have capacity for them all? Will some Southern services be withdrawn as a result?
The 'extra' Thameslink core services have always been intended to be provided mainly by diverting services off the existing networks, originally the balance of 'ex-Southern' and 'ex Southeastern' was going to be slightly different, but the 2012 decision by DfT (the one mainly remembered for keeping the Wimbledon/Sutton loop service as a through service) changed the routes so that 16 tph come through New Cross Gate to Thameslink, and none come from the Southeastern division through London Bridge.
The combined number of services through the London Bridge throat, split onto the four groups, terminating/Charing Cross/Cannon St/Blackfriars will probably be around 86-88 trains per hour or so - not that much different to today.
In summary, early plans (prior to 2012) were for
London Bridge through to Thameslink (18 tph)
4 tph ex Southeastern routes
14 tph ex Southern routes
Elephant & Castle through to core (6 tph)
6 tph ex Southeastern routes
Current plans (from 2012) are for
London Bridge through to Thameslink (16 tph)
16 tph ex Southern routes
Elephant & Castle through to Core (8 tph)
4tph from Southeastern routes
4 toy from Southern (Wimbledon/Sutton)
And does that mean the SouthEastern lines will not see any service improvement as a result of the London Bridge rebuild?
As said in previous answer - there will be a general improvement in pathing, but some origins will have long term alterations of terminal station, i.e. the options of Cannon St or Charing Cross will change as the routes are rationalised, with Cannon St being a 7 day terminus for certain service groups.
What is notable is that the original plans had always assumed a 10 tph total coming from the 'Southeastern' network, but apparently their 'stakeholders' never actually wanted trains from origins such as Tunbridge Wells to divert from Cannon St into the Thameslink core. The net effect of Southeastern reluctance and Wimbledon/Sutton loop loud insistence has been to shift the balance considerably from Southeastern to Southern.
--- old post above --- --- new post below ---
Isn't there going to be a very large concourse below platforms too? Certainly is on most of the plans i have seen.
That was what I meant by a 'common ground level concourse' [i.e. common to all platforms] in my post #3 above, although it could have been better phrased...