With work already started on the upgrading/new build of the M8 between Baillieston and Newhouse I was wondering how this will affect services on the Glasgow - Whifflet Line.
The plans are to build a new, 2nd "Cutty Sark" bridge crossing 6 lanes of newly built M8 motorway almost immediately west beyond the original bridge crossing the current 4 lane A8.
I've been racking my brains as to how to can do this without closing the Whifflet line for a prolonged period of time. They would be adding a new massive bridge to an already existing regularly used passenger and freight line.
Would they essentially build a tunnel for the new M8 and on completion of that section of road, build a bridge over the tunnel section over the course of a weekend then dismantle the tunnel underneath. The plans show a rail over-bridge and not a motorway tunnel.
The answer is probably obvious, but I just can`t think what it would be. Anyone got any ideas.
The plans are to build a new, 2nd "Cutty Sark" bridge crossing 6 lanes of newly built M8 motorway almost immediately west beyond the original bridge crossing the current 4 lane A8.
I've been racking my brains as to how to can do this without closing the Whifflet line for a prolonged period of time. They would be adding a new massive bridge to an already existing regularly used passenger and freight line.
Would they essentially build a tunnel for the new M8 and on completion of that section of road, build a bridge over the tunnel section over the course of a weekend then dismantle the tunnel underneath. The plans show a rail over-bridge and not a motorway tunnel.
The answer is probably obvious, but I just can`t think what it would be. Anyone got any ideas.