There was also a period where EWS cut back on the number of guards they supplied to relaying sites. I was once on a site a mile long with six trains and we only had one guard. She was not well and having seen her drag herself from one end of the job to the other a couple of times, the Relay Supervisor directed one of his men with a van to drive her back and forth. The site end marker boards being moved to coincide with access points.
On a smaller sites we would often have no guard at all, the trains coming up to the site marker boards DOO then waiting for a guard before they would come on site. We were sometimes reduced to ringing the PIC and shortening the site on the road next to the hole so it started twenty yards past the end of the dig. We would then move the boards, and have the PIC ask the driver to move up to the board. Once the train was opposite the hole we would then agree with the PIC that we would extend the site back clear of the train move the boards back and then start loading or unloading it.
Madness but what else can you do when you have a huge great hole in the track, time is running out and a bottom ballast train with no guard. It was no use complaining to EWS as they were only liable for a certain level of charges for failure to provide trains and staff. Which they generally exceeded in weeks from the start of the year, after that they could do what they liked. Provided a train arrived on site we had to pay for it regardless if it was useable or not.