This is now on the ORR web site: http://www.rail-reg.gov.uk/pr13/publications/final-determination.php
NR has got some but by no means all of the increases it wanted from the draft in June.
From a quick read:
- a number of projects, including Northern Hub, Electric Spine (except MML) and East West Rail, are placed in a category where spend is conditionally approved, pending better costings at GRIP3 stage
- Northern Hub funds are not ring-fenced
- Carstairs remodelling and Edinburgh South Suburban electrification are not approved (not in HLOS)
- GW and MML electrification costs are up by £376m
- Uckfield electrification is not approved (not in HLOS)
- ETCS cab fitment (NR funds the "first in class") will now be a development project rather than a renewal cost
- NR signalling strategy (concentration in ROCs) is approved
- the cost of traction electricity seems to have come down significantly in the past year; this is at odds with the domestic situation!
- helicopter inspection patrols of the overhead kit on the WCML
- WC, EC and GW long-distance services will be on a different PPM measure to the other TOCs.
They will be targeted on 88% PPM with additional targets on significant lateness
- more level crossing replacement spend
I'm sure there is more in the small print.
NR has got some but by no means all of the increases it wanted from the draft in June.
From a quick read:
- a number of projects, including Northern Hub, Electric Spine (except MML) and East West Rail, are placed in a category where spend is conditionally approved, pending better costings at GRIP3 stage
- Northern Hub funds are not ring-fenced
- Carstairs remodelling and Edinburgh South Suburban electrification are not approved (not in HLOS)
- GW and MML electrification costs are up by £376m
- Uckfield electrification is not approved (not in HLOS)
- ETCS cab fitment (NR funds the "first in class") will now be a development project rather than a renewal cost
- NR signalling strategy (concentration in ROCs) is approved
- the cost of traction electricity seems to have come down significantly in the past year; this is at odds with the domestic situation!
- helicopter inspection patrols of the overhead kit on the WCML
- WC, EC and GW long-distance services will be on a different PPM measure to the other TOCs.
They will be targeted on 88% PPM with additional targets on significant lateness
- more level crossing replacement spend
I'm sure there is more in the small print.