Electrification of GWML around Reading

Status
Not open for further replies.

Andrewlong

Member
Joined
2 Jan 2013
Messages
373
Location
Earley
The masts have started to go up east of Reading station near to the old gas tower. They can be seen from the Waterloo line. I will provide photos of progress if no one else can.

Can anyone in the know tell me the plans for completion of electrification by phase ?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

anthony263

Established Member
Joined
19 Aug 2008
Messages
6,892
Location
South Wales
I think the plan is to install the wires at Reading while they are doing the rebuilding work so they dont have to come back and cause more disruption later.

The wires are supposed to be at Oxford by early 2016 so if true I would suspect the wires will be up between Reading & Airport Junction by around late 2015.
 

MK Tom

Established Member
Joined
31 Aug 2011
Messages
2,458
Location
Milton Keynes
Could Reading terminating services go electric sooner than Oxford then?

The rebuild of Reading is HUGELY ahead of schedule so we may even see the wiring of the GWML come earlier than planned too. The EMU depot west of Reading already has masts up.

I'd love to see pictures of the new masts to the east if possible.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,274
The rebuild of Reading is HUGELY ahead of schedule so we may even see the wiring of the GWML come earlier than planned too. The EMU depot west of Reading already has masts up.

Are you referring to the original schedule, or the current accelerated schedule? At one stage NR took about 12 months (or more) out of the original overall project - so are they also running ahead of the revised dates?

http://www.networkrailmediacentre.c...-ONE-YEAR-EARLY-AS-EXHIBITION-OPENS-TO-PUBLIC

The latest CP4 milestones (Dec 2012), published last week, still give the dates as follows:

New platforms by May 2013 - (but due April 4th)
New Depot by November 2013
Reading West grade separation Dec 2014
West Country grade separation (up Westbury line) by April 2015
 

D365

Veteran Member
Joined
29 Jun 2012
Messages
13,180
It's good that the Reading rebuild is coming on well before the original schedule. Keep it up guys!

;)
 
Last edited:

mr_moo

Member
Joined
7 Sep 2009
Messages
649
Location
Cambridgeshire
Don't forget that wiring of Heathrow Junction to Maidenhead is part of the Crossrail project and is thus mixed in with much greater works. Wires need to be up for GW trains and IEP by 2016 although Crossrail wont use them till 2018.

There's such a big prgramme of works associated with wiring that it's unlikely to be brought forward. don't forget about bridge reconstruction (going well - see the Network Rail youtube channel for the three bridges we demolished over Christmas), track lowering, re-signalling, bridge parapet raising, paddington platform works (electricfication of the remaining platforms that don't currently have wires), significant trackwork remodelling at Maidenhead to support the reversals, track mods at Slough and Iver-West Drayton....

There's lots to do! :)
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,274
There's a calendar in the new 2013 'Western route' business plan, which splits all the electrification into about 10 major phases. The numbered phases jump around a bit as you can see, which possibly means that a particular area might get the wires up but they won't actually connect anywhere either side, eg phase 3 seems to be west of Reading but happening before phases 1 and 2...

Details on page 62 in here: http://www.networkrail.co.uk/browse...ture plans/route plans/western route plan.pdf
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,918
Location
Mold, Clwyd
There's this text on p62 of the Strategic Plan:

We have continued the development of our costing for schemes since we published the IIP. The most significant changes in costs compared to those assumed in the HLOS includes:

Proposed expenditure on Great Western electrification has increased by over £300m due to increased scope (including new bridge reconstructions) and the development of an electrification system that meets the requirements of European regulations and those of new trains

The inclusion of funding to complete Reading which was absent in the HLOS

This totals the thick end of £500m extra spend.
By contrast the estimates for NW/TP electrification have come down by £100m.
 

Pumbaa

Established Member
Joined
19 Feb 2008
Messages
5,022
Depot's on course for Summer completion.

Are you referring to the original schedule, or the current accelerated schedule? At one stage NR took about 12 months (or more) out of the original overall project - so are they also running ahead of the revised dates?

http://www.networkrailmediacentre.c...-ONE-YEAR-EARLY-AS-EXHIBITION-OPENS-TO-PUBLIC

The latest CP4 milestones (Dec 2012), published last week, still give the dates as follows:

New platforms by May 2013 - (but due April 4th)
New Depot by November 2013
Reading West grade separation Dec 2014
West Country grade separation (up Westbury line) by April 2015
 