Anyone know when the big blockade of Nottingham station is happening to redo signals and junction layouts?
Civils complete* December 2012
Signalling installation complete* June 2013
Blockade starts July 2013
Blockade completion August 2013
GRIP 6 completion January 2014
* pre-blockade works only.
CP4 enhancement plan update Dec 11