Will it be pan up/down in the Gledholt tunnels for a couple of years at the end of this decade?

Jamesrob637

Established Member
Joined
12 Aug 2016
Messages
6,080
Moderator note: Split from

So will it be pan up/down in the Gledholt tunnels for a couple of years at the end of this decade?
 
Last edited by a moderator:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,670
Yes and then realistically only the 802s as the new TPE stock is a long way off. Looking at the timeline I don't think Northern will have new EMU stock to use by time Leeds-Huddersfield is live.
 

fat_boy_pete

Member
Joined
16 Mar 2015
Messages
368
Location
Essex
Yes and then realistically only the 802s as the new TPE stock is a long way off. Looking at the timeline I don't think Northern will have new EMU stock to use by time Leeds-Huddersfield is live.
Better that a substantial and useful (Leeds-Huddersfield) route is available to bed in new stock, rather than mouldering in a siding after delivery.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,935
Location
Mold, Clwyd
Personally I would assume in Huddersfield station itself. So visible pantograph movement and dwell time available to resolve any transient issues.
If they wire through the tunnels to Springwood Jn (with an overlap towards Marsden) EMUs terminating from the east would be able to run as ECS and reverse west of the tunnels back into the station.
Otherwise the station is the obvious place to switch power with 802s.
 

waverley47

Member
Joined
17 Apr 2015
Messages
853
If they wire through the tunnels to Springwood Jn (with an overlap towards Marsden) EMUs terminating from the east would be able to run as ECS and reverse west of the tunnels back into the station.
Otherwise the station is the obvious place to switch power with 802s.

There's two slow through platforms, and a six car bay platform, going in at Huddersfield for exactly that reason. Reversing on the main line at Springwood Jn would eat capacity needlessly.

The general plan is for the Mancs - Hudds stopper to terminate in the new platform 3, and the Leeds - Hudds and Bradford - Hudds stoppers to terminate in the new platforms 5/6.
 
Last edited by a moderator:

superkev

Established Member
Joined
1 Mar 2015
Messages
2,866
Location
west yorkshire
So will it be pan up/down in the Gledholt tunnels for a couple of years at the end of this decade?
One of Tim's Youtubes looked to show mast bases for a short distance west of the tunnels. Perhaps to permit west end shunting between platforms at times of disruption.