• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

ORR Track Access Dashboard

Status
Not open for further replies.

deltic

Established Member
Joined
8 Feb 2010
Messages
3,714
The ORR has just published a track access dashboard https://app.powerbi.com/view?r=eyJr...3OTk2LTdmM2EtNDM5NC04MGY1LTQ2MGNiYzA3NjEzYiJ9 which shows the extent that operators use their contractual paths on the network.

If I understand the numbers correctly West Midlands only runs 65% of the paths it has rights to and Merseyrail 68%. LNER runs 74% while at the other end of the scale are Chiltern who run 96%. Although if you drill down into the detail it appears C2C runs more trains on Saturdays than it has paths.

It also lists live applications some of which I thought had been approved such as Stirling to London.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

takno

Verified Rep - Traksy
Joined
9 Jul 2016
Messages
6,578
The ORR has just published a track access dashboard https://app.powerbi.com/view?r=eyJr...3OTk2LTdmM2EtNDM5NC04MGY1LTQ2MGNiYzA3NjEzYiJ9 which shows the extent that operators use their contractual paths on the network.

If I understand the numbers correctly West Midlands only runs 65% of the paths it has rights to and Merseyrail 68%. LNER runs 74% while at the other end of the scale are Chiltern who run 96%. Although if you drill down into the detail it appears C2C runs more trains on Saturdays than it has paths.

It also lists live applications some of which I thought had been approved such as Stirling to London.
As discussed in another thread, it's worth bearing in mind that this is usage of the paths which ORR has granted rights to. It doesn't relate to actual workable paths for trains. In particular rights on the East Coast were granted to LNER on the assumption that various engineering interventions would be made along the whole length of the line. Not only have some of those interventions not been completed, but the theoretically "possible" new timetable has now been pushed back by several years and doesn't show much sign of actually being implemented within any of our lifetimes. This means that Network Rail aren't able to offer LNER the number of paths they are entitled to or would like to run.

In the case of Merseyrail and West Midlands it's likely that various paths aren't being used due to commuter flows not really justifying them anymore.

Also worth checking which set of figures you are looking at, since at least some of the figures measure actual trains run against theoretical paths, so not only can the operators sometimes not get the paths, but any cancellations due to strike action or staff and stock shortages are also thrown against them.
 

eastlondon000

New Member
Joined
12 Jul 2024
Messages
1
Location
London
As discussed in another thread, it's worth bearing in mind that this is usage of the paths which ORR has granted rights to. It doesn't relate to actual workable paths for trains. In particular rights on the East Coast were granted to LNER on the assumption that various engineering interventions would be made along the whole length of the line. Not only have some of those interventions not been completed, but the theoretically "possible" new timetable has now been pushed back by several years and doesn't show much sign of actually being implemented within any of our lifetimes. This means that Network Rail aren't able to offer LNER the number of paths they are entitled to or would like to run.

In the case of Merseyrail and West Midlands it's likely that various paths aren't being used due to commuter flows not really justifying them anymore.

Also worth checking which set of figures you are looking at, since at least some of the figures measure actual trains run against theoretical paths, so not only can the operators sometimes not get the paths, but any cancellations due to strike action or staff and stock shortages are also thrown against them.
It's worth noting that for passenger services like those you're discussing, access rights don't grant access to a 'path', but rather to the right to run a service (e.g. Section 5 : the type of train, frequency, calling pattern, number per day etc). The figures don't measure 'theoretical paths', but measure the access rights that the Train Operating Company hold, and the number of services they are planning to run, and finally the number of services they actually run. The operators should adjust their access rights in accordance with the services they decide to run (e.g. in the case of Merseyrail and West Midlands), and can do this (they were originally supposed to use Part J2 of the Network Code for this, but never have for some reason, though I think freight does). Not disputing your point about the weaknesses of Network Rail at all in terms of planning though !

Would be interested to hear thoughts on the dashboard - it's received very little attention, which makes sense because of how unintuitive it is to navigate, but there's a lot on there. Even Rail UK seems to misunderstand access rights though...
 
Status
Not open for further replies.

Top