Was just thinking of a potential conundrum in unit diagramming.
Let's say a small network requires 25 units in total, including those used only in the peak.
There are two ways of diagramming the off-peak service. You either have 10 units in service off-peak with shorter turnaround times, or 12 units in service off-peak with longer turnaround times.
Let's say platform occupancy isn't an issue, i.e. there is no platform occupancy limitation to prevent the 12-unit solution.
Is there any particular advantage in minimising the number of units out off peak, and going for the 10-unit solution? Mileage-wise both would be equivalent, you either have 10 units on a high mileage per unit or 12 units on a slightly lower mileage per unit, but total mileage the same. And 13-15 units are only used in the peak in any case.
Let's also say the units are cycled so you don't get the same 10 or 12 units out on off-peak duties each day, i.e. each unit gets a number of peak-only days.
So if the 12-unit solution involves some advantage, such as slightly longer turnaround times (and thus increased reliability) or simpler diagramming, is there any good reason to not choose it over the 10-unit solution?
Let's say a small network requires 25 units in total, including those used only in the peak.
There are two ways of diagramming the off-peak service. You either have 10 units in service off-peak with shorter turnaround times, or 12 units in service off-peak with longer turnaround times.
Let's say platform occupancy isn't an issue, i.e. there is no platform occupancy limitation to prevent the 12-unit solution.
Is there any particular advantage in minimising the number of units out off peak, and going for the 10-unit solution? Mileage-wise both would be equivalent, you either have 10 units on a high mileage per unit or 12 units on a slightly lower mileage per unit, but total mileage the same. And 13-15 units are only used in the peak in any case.
Let's also say the units are cycled so you don't get the same 10 or 12 units out on off-peak duties each day, i.e. each unit gets a number of peak-only days.
So if the 12-unit solution involves some advantage, such as slightly longer turnaround times (and thus increased reliability) or simpler diagramming, is there any good reason to not choose it over the 10-unit solution?