Metropolitan Line Signalling

Kevin51

Member
Joined
12 Dec 2019
Messages
61
Location
Herts
Did the Metropolitan Line ever get a new signalling system? In 2009 I was working on enabling works for the new system. I also had a friend working on the main system in 2011/12. Just there is a lot of chat on a local group about signalling problems in the Wembley Park/Preston Road area. There was the inevitable comment about the Metropolitan Line being 150 years old so what to you expect. Just wondered if they did ever install a new state of the art system. Seems like they didn't.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
Did the Metropolitan Line ever get a new signalling system? In 2009 I was working on enabling works for the new system. I also had a friend working on the main system in 2011/12. Just there is a lot of chat on a local group about signalling problems in the Wembley Park/Preston Road area. There was the inevitable comment about the Metropolitan Line being 150 years old so what to you expect. Just wondered if they did ever install a new state of the art system. Seems like they didn't.
They are in the process of installing it, here is the thread discussing the project: https://www.railforums.co.uk/threads/ssr-resignalling.166182/

It covers all 4-subsurface lines (Circle, Hammersmith and City, District, and Metropolitan), and has currently covered the entire H&C and Circle lines, the Met south of Preston Road, and the District east of Barons Court.
The eventual plan will see the entire Met line converted (with Chiltern sharing the tracks on normal signals), but will leave the sections of the District line shared with other lines/trains on the existing signalling.

See also the wikipedia page: https://en.wikipedia.org/wiki/Four_Lines_Modernisation
 
Last edited:

Kevin51

Member
Joined
12 Dec 2019
Messages
61
Location
Herts
I will take a look. A friend of mine was working on the design back in 2011/12, that was 14 years ago. Didn't the fire the original designer? Why is the taking sooooooooooooooooo long. I suppose everybody involved wants it to take as log as possible.
 

Pegpilot

Member
Joined
26 Mar 2020
Messages
114
Location
Northants
The original SSL signaling contract was let by Bombardier, an equity partner in the Metronet PPP Consortium (I was a Metronet employee at the time). They plumped for Westinghouse. The whole thing was a bit of a mess as I recall disputes about who was responsible for all the enabling works like equipment rooms and cable runs. So, the whole thing sorry debacle was binned when Metronet collapsed and TfL took control. As for me, I crossed the street to Tube Lines on Metronet's demise and found an altogether more structured and disciplined approach to programme management. In retrospect, delivered Jubilee Line resignaling just two years late was a paragon of virtue compared with multiple false starts on 4LM !
 

Kevin51

Member
Joined
12 Dec 2019
Messages
61
Location
Herts
I see that they eventually went for the Thales Seltrac system that is used on the DLR, Jubilee and Northern Lines. Why on Earth didn't LU do for Seltrac in the first place
 

Old Walter

Member
Joined
26 Aug 2025
Messages
48
Location
Ilford
From memory, by 2011 the Westinghouse project had gone - and the product on the table then was Bombardier Cityflo 650 (and C650 was planned to be on the whole SSR & Piccadilly line). The proposals at that time were a lot bigger than happened - for example the two sets of crossovers at Hammersmith (H&C) were to be replaced by a scissors crossover and one of the crossovers at Amersham was to be replaced the other way round to enable straight reversing from southbound platform 3.

I believe a lot of the reversing points would have stayed in on that scheme, but in the end on the (then) Thales scheme a lot of areas got simplified to make the project easier. Some extra moves at different places did get put in though with CBTC operation.
 

Harpo

Established Member
Joined
21 Aug 2024
Messages
3,733
Location
Newport
Sounds very similar to the woes upstairs, sifting through supplier promises of limitless supplies of free gifts and airware in their products but occasionally failing to spot the duds.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
Just there is a lot of chat on a local group about signalling problems in the Wembley Park/Preston Road area.
Another thread reports a cracked crossing at points in the Wembley Park area, which apparently are hard to get overnight access to replace due to Night Tube hours.


This kind of failure would not be specifically related to the type and age of signalling in use.
 

Pegpilot

Member
Joined
26 Mar 2020
Messages
114
Location
Northants
I see that they eventually went for the Thales Seltrac system that is used on the DLR, Jubilee and Northern Lines. Why on Earth didn't LU do for Seltrac in the first place
Well, back then it wasn't LU's decision - the choice of technology and contractor had been abdicated to the PPP Contractors. As I recall, there were concerns that Seltrac was incapable of dealing with complex layouts, as was demonstrated when they struggled with the delts junction on DLR at Poplar. And the Jubilee was much closer to the ideal end-to-end layout that would make life easier for the contractor (if one sets aside the Met inter-running issues).
 

Kevin51

Member
Joined
12 Dec 2019
Messages
61
Location
Herts
Well, back then it wasn't LU's decision - the choice of technology and contractor had been abdicated to the PPP Contractors. As I recall, there were concerns that Seltrac was incapable of dealing with complex layouts, as was demonstrated when they struggled with the delts junction on DLR at Poplar. And the Jubilee was much closer to the ideal end-to-end layout that would make life easier for the contractor (if one sets aside the Met inter-running issues).
When you say back then, Metro net went under in 2007. TfL took over Tubelines in 2010. Not withstanding LU having approve everything that Thales did after 2010 every thing was down to LUL as part of TfL. I did have a damn good laugh, I was with Thales when it was Alcatel in 2005 I think through to 2007. I was then with Tubelines in 2009 as part of Tublines team putting together the claim to LUL. When TL got the response back LU said they rejected the claim for increased costs, LU just said that TL had stated in monthly reports that lack of progress was totally due to poor performance by Thales. TL had agreed the Thales claim to TL. I very nearly split my sides laughing when I read how TL had shot themselves in both feet.
 

Pegpilot

Member
Joined
26 Mar 2020
Messages
114
Location
Northants
And that failed "frustrated access" claim by Tube Lines, combined with TfL and Tube Lines failing to agree commercial terms for the second contract review period, led to TL handing back the keys. Big losers were Picc line passengers, as the contract award process for 73 TS replacement was well advanced (I know, I was on the bid evaluation team) and that project got canned in the mayhem of the moment. So the first new Picc train might have been in service 13 years ago. Funny old world !
 