Have just had a leaflet through the door announcing a five day line block Chichester, Petersfield and Portsmouth, between 26th - 30th October to replace aging signaling equipment.

Now considering Havant was completely resignalled in an expensive and notoriously wildly over running project in - I think - 2007, and the route to Chichester in 1992, what is life expired?

Is it that the 2007 project was just the wrong thing?

The work is part of our £120 million Havant re-signalling programme, the next phase of the wider Portsmouth Direct Upgrade.

The Havant Relock & Recontrol project, the main reason for the blockade, will replace ageing signalling and interlocking equipment in the Havant area and modernise the way the railway is controlled.

Control of the railway will move from Havant Area Signalling Centre to our Basingstoke Regional Operational Centre (ROC).

The work includes:
  • installing 61 axle counters (equipment that detects when trains enter and leave sections of track)
  • installing 23 automatic warning system (AWS) and nine train protection and warning system (TPWS) components, which provide drivers with warnings and help to keep the railway safe
  • refurbishing cable routes and installing new fibre and power cabling to provide the connections needed for the signalling system
  • installing new signalling equipment and associated infrastructure
  • carrying out testing and preparatory work for the wider re-signalling programme
  • carrying out track, third rail, switch, level crossing and other infrastructure maintenance while the railway is closed
 
Last edited by a moderator:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

satters

Member
Joined
25 Mar 2020
Messages
59
Location
Stourbridge
also that 20 years for electronics means obsolescence, whereas relay equipment will last many more decades, and mechanical even more still, yet there is always now the drive to use electronics despite the shortcomings in short life and failures
 

Swedenorer

Member
Joined
28 Sep 2025
Messages
310
Location
Hants
Thanks for the link and the confirmation of my suspicion - yes I have been clobbered by that unreliability quite a few times. Funnily enough I was told by a railway staff member when the project was in preparation that he thought it was a poor solution. But to only get 19 years out of it...
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,290
Thanks for the link and the confirmation of my suspicion - yes I have been clobbered by that unreliability quite a few times. Funnily enough I was told by a railway staff member when the project was in preparation that he thought it was a poor solution. But to only get 19 years out of it...
They’ve still got a major ROC to fill of course, I wonder how that affects their decision making process…
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,582
Location
Torbay
There was a Railtrack initiative to broaden the signalling supplier base, which led to Siemens setting up new teams to customise their German Simis W equipment for British use.

The SIMIS architecture of that time was very cable-intensive, concentrating i/o in equipment rooms covering a large area, not unlike former remote relay interlockings.

This contrasts with the more typical modern UK approach, using distributed trackside functional modules (object controllers) in cabinets much closer to the trackside objects themselves. Experience from the Portsmouth scheme led to Siemens losing a major framework contract for further sites in the south east.

Siemens later regrouped and re-entered the UK market by purchasing the rail control business of Invensys, including former Westinghouse product lines (SSI and successors) and a couple of former BR signalling design offices.

== Doublepost prevention - post automatically merged: ==

They’ve still got a major ROC to fill of course, I wonder how that affects their decision making process…
It clearly means control will likely migrate there, but just having the space there waiting wouldn't have hastened the work, which is primarily to address performance and eliminate unusual equipment that is now difficult to support.

SIMIS W was first installed at Bournemouth, then around Portsmouth, but despite ambitious plans for further rollout, the technology was never used elsewhere.
 
Last edited by a moderator:

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,290
It clearly means control will likely migrate there, but just having the space there waiting wouldn't have hastened the work, which is primarily to address performance and eliminate unusual equipment that is now difficult to support. SIMIS W was first installed at Bournemouth, then around Portsmouth, but despite ambitious plans for further rollout, the technology was never used elsewhere.
Is Bournemouth going to need early replacement too?
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,582
Location
Torbay
Is Bournemouth going to need early replacement too?
Likely yes, eventually, but I doubt the performance pressures are so great. It's a simpler layout, and presumably recovered parts from Portsmouth might become spares for Bournemouth.
 

Sun Chariot

Established Member
Joined
16 Mar 2009
Messages
6,680
Location
2 miles and 50 years away from the Longmoor Milita
Have just had a leaflet through the door announcing a five day line block Chi, Pfield, Pompey 26th - 30th October to replace aging signaling equipment
Thanks for the insight. We are just round the corner from Bedhampton station, yet no leaflet through our door. I'll get myself very familiar with RRB timings...
 
Last edited:

Swedenorer

Member
Joined
28 Sep 2025
Messages
310
Location
Hants
Bedhampton Crossing closing for the week too...

Given the time and cost over-runs of the 2007 scheme I wonder what the return on that investment was - if any.
 

MadMac

Established Member
Joined
13 Jun 2008
Messages
1,500
Location
Moorpark, CA
Siemens showed up at my L.A. office hawking their wares while the Portsmouth debacle was in full swing. They realised the game was up when I mentioned that I understood they were having some issues there…..
 