• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

First ETCS train operates on the East Coast Mainline

bramling

Veteran Member
Joined
5 Mar 2012
Messages
20,407
Location
Hertfordshire / Teesdale
I’ve never heard of redundant signals being reused, except rarities on preserved railways, and some components into spares (ef certain tyoes of signal heads).

To put it in context, a resignalling project with 200 new signals might cost £200m pounds, but the materials cost of the actual signals (post and signal head) will be, at the very most, 1% of that. Driver briefing and training will cost more.

LT certainly used to re-use old signals during resignalling projects. If you look at something like the Bakerloo, resignalled in the late 80s, most of the signal heads are much older than that. Same applies on a lot of the Piccadilly Line.

I’m not sure of the extent to which signals were retained in situ where practicable versus parts going into store, being refurbished, and installed in new schemes.

This generally stopped in the 1990s, the Central Line used new signal heads, although many old ones were retained as part of the interim stage works.

I think I also remember that the rushed interim signalling scheme on the Jubilee Line Extension re-used old train stops.

Presumably a lot removed during the various PPP-era line upgrade schemes has gone in the bin, though amazingly there’s still a few old signal heads left redundant in situ for over a decade now. Quite poor really, as it’s asking for problems if any part of the structure corrodes.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,620
Location
Northampton
Agreed that if you design the system from the outset as a conventional signalling overlay on an underlying ETCS signalling system, then it will be easier to recover the signals. But the costs will still be significant.

Where there are signals, the ETCS cannot work independently of the signals. The driver must not get conflicting information from the ETCS and the lineside signalling. So either the ETCS movement authorities must be synchronised with what the lineside signals are showing, or the lineside signals must be synchronised to the ETCS (such as by displaying a special "ETCS aspect"). It follows that when you recover the signals, you have not only got the costs of physically recovering the signals themselves, and their associated hardware (object controllers, equipment cases, cabling alterations, etc), but you will have significant software changes to make to the underlying control systems as well. Designing, implementing and testing these kind of alterations doesn't come cheap, and I doubt that the costs would ever be recouped from the savings in maintenance costs. After all, signals don't need much maintaining.

And you need to cost in the disruption to services caused while you make all these alterations.

And they involve the kind of software changes that only the original system supplier will likely be capable of doing. If they are using their limited resources for such recoveries, they won't be able to use them for other resignalling work, further ETCS roll-out, etc.
The transition from Overlay to Signals-Away requires all these changes whether the signals are physically retained or not, doesn't it?

Given one of the justifications for Signals-Away is the reduction in maintenance benefit, I could see a recovery programme of assets in diruptive positions (i.e. 10-foots or on Gantries) after Signals are switched off. But as you note, the disruption of recovering them will mean they likely won't be gone in the same possession they are switched off.

Also all the reasons you mentioned above are why NR are keen to phase ETCS in so that after a 'pathfinder' area the adjacent schemes can go straight from no ETCS to Signals-Away.
I think such recoveries are a nice idea in theory, but I really can't see them ever being justified in practice.
Recovery was justified on the NCL for at least some signals. Not sure if they've left the ones in the tunnel but they did at least one for the publicity shots. However Heathrow branch has notably kept it's signals and GW-ATP despite all trains being ETCS on the branch so I suspect there'll be a case-by-case assessment for recovery.
 

bahnause

Member
Joined
30 Dec 2016
Messages
1,039
Location
bülach (switzerland)
3.6.0 is the baseline that will be used for the forseeable future.
We should gradually start to abandon the idea, that the end customer has much of a choice in this matter. At the end of the day, it is the industry that dictates the standards for ETCS. The BL 3.6.0 in particular has glaring shortcomings in its specification, which can only be rectified by using BL4. The Stadler DuFour for SBB Cargo is one such example where BL4 will already be used.
 

Top