    Crossrail - Construction updates and progress towards opening (now expected 24 May 2022)

    Just come in from David Pearce, Elizabeth Line delivery manager, that they have accepted the 70th and final class 345 (345018) into traffic. https://www.linkedin.com/feed/update/urn:li:activity:6925157504838492162/
  2. D

    Crossrail - Construction updates and progress towards opening (now expected 24 May 2022)

    And once the ORR have granted full authorisation for the line and stations which should, hopefully, be due imminently.
  3. D

    East Kilbride/Barrhead electrification updates

    There's also one at Priesthill & Darnley station. I'd imagine they would take a similar approach with that one to what they did at Cumbernauld back in 2014 in that they build a new bridge (with improved station access) and demolish the existing one. The current one at Darnley is old, overgrown...