Preventing engineering handback will obviously delay the entire possession handback live for the operational railway.
I was referring to the handback of the project under PACE. I could have wrote that better to be fair.
Upon completion of the work, a representative of the maintenance organisation will inspect the work for any snags or defects. This will include scrap. These inspections are often completed a later date. Under the AMP process and PACE, the site still remains the responsibility of the contractor until the maintainer agrees there are no snags or defects.
I think there has historically been a bad attitude to scrap removal, especially of ‘smalls’ like clips and pads. In a lot of areas now, the maintainer will not sign they are happy with the work until all scrap is removed.
There are many ways to allow for scrap removal which aren’t within the posession. Including a further ‘scrapping out’ shift or positioning scrap where it can be collected without going on track, like at access points.