I thought I'd revisit the project plan (this is my post below summarising it
from 27th January 2026) and look at how things are progressing.
Aberdare toilets:
yes, completed
Merthyr Vale toilets: not sure (National Rail and TfW's website says no)
Treorchy toilets: not sure (National Rail and TfW's website says no)
Merthyr Tydfil toilets: not sure (National Rail and TfW's website says no)
Abercynon toilets: not sure (National Rail and TfW's website says no)
Tonypandy toilets: not sure (National Rail and TfW's website says no)
Cardiff Bay wires: completed - live and in use by 398s. Wires were live at the end of May, so two months later than planned.
Ty-Glas platform extension: completed 4th April 2026 (pretty much to plan)
Cwmbach toilets: not sure (National Rail and TfW's website says no)
Llwynypia toilets: not sure (National Rail and TfW's website says no)
398s on Cardiff Bay - Pontypridd: yes, in service as of July 2026, so around 3 months behind schedule
398s on TAM lines: not started
756s on Barry Island trains: yes, now in service (though still plenty of 231s on that route)
Additional feeder at Ninian Park: not clear but likely taking place during evening shutdowns this week (10th-15th August)
Bute Town station: work still in progress, no announcement made
It's worth noting that the key event of this year is the timetable change in December. If TfW can get enough 398s in service reliably to cover the Pontypridd-Cardiff Bay diagrams, that will allow them to remove the 150s from those routes and they can bring in the new timetable with its faster times between stops.