Network Rail are finalising plans for what looks like a month-long shutdown of all trains west of Chester. (making a pure assumption the Bidston line will still run but the Conwy Valley line wont)

Set for January 2027.

Public info states it's for "the construction of two new fully accessible footbridges, extensive track renewals and drainage enhancements along the North Wales Coast line". Must be an awful lot of renewals and drainage due to shut down the whole line for a month?

 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

The exile

Established Member
Joined
31 Mar 2010
Messages
9,319
Location
Somerset
Network Rail are finalising plans for what looks like a month-long shutdown of all trains west of Chester. (making a pure assumption the Bidston line will still run but the Conwy Valley line wont)

Set for January 2027.

Public info states it's for "the construction of two new fully accessible footbridges, extensive track renewals and drainage enhancements along the North Wales Coast line". Must be an awful lot of renewals and drainage due to shut down the whole line for a month?

What it actually says is that it includes those things.
 

Simon11

Established Member
Joined
7 Nov 2010
Messages
1,389
Would be a great opportunity to stick in electrification infrastructure too albeit our Government and GBR are not ready nor prepared.
 

Tomos y Tanc

Member
Joined
1 Jul 2019
Messages
916
Yes, which is the only public info at present. I'd imagine it includes a plethora of other work too.
Pity there's nothing about replacement of foot crossings or level crossing access to caravan parks. They're a real problem. Still, glass half full and all that. Nice to see the line getting some TLC for once.
 

Sheridan

Member
Joined
11 Jan 2012
Messages
616
Pity there's nothing about replacement of foot crossings or level crossing access to caravan parks. They're a real problem. Still, glass half full and all that. Nice to see the line getting some TLC for once.

I think it does say that, albeit not explicitly - but the bit about accessible footbridges surely includes the one at Abergele which will result in the closure of Tŷ Gwyn and Pen Uchaf foot crossings?
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
Haven't the foot crossings already been closed?
That's what allowed the recent service increase to 3tph on the NW main line.
The new work in January is (among other things) to construct the new footbridges, so this summer there will be a lack of access across the railway in places.
 

Sheridan

Member
Joined
11 Jan 2012
Messages
616
Haven't the foot crossings already been closed?
That's what allowed the recent service increase to 3tph on the NW main line.
The new work in January is (among other things) to construct the new footbridges, so this summer there will be a lack of access across the railway in places.

Sandy Lane and Beverley Drive in Prestatyn have closed, but Tŷ Gwyn and Pen Uchaf remain open, as unlike the Prestatyn crossings, these are equipped with red and green lights, and as an additional measure there are crossing attendants at both of them during the day.
 