• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Recent content by superkev

  1. S

    Transpennine Route Upgrade and Electrification updates

    Thanks, almost ready for the track then. To me then the only remaining obstructions to completing the fast tracks look to be the Ravensthorpe flyover box, and demolition of Leeds road old bridge. Perhaps there are more. K
  2. S

    Transpennine Route Upgrade and Electrification updates

    Regarding Baker viaduct, the latest Youtube video shows most of the precast decking segments in place with just the River and canal section to do. Some people have speculated an additional surface deck will be cast on top, but I'm not so sure. There's a usefull description at...
  3. S

    Transpennine Route Upgrade and Electrification updates

    Tim's Youtube also shows Austhope Lane bridge East of Leeds has had repacement decks lifted in by a huge crane during the weekend closure. Not many bridges left to start work on east of Huddersfield. K
  4. S

    Transpennine Route Upgrade and Electrification updates

    Latest Robert Stenhouse Flickr pictures shows Calder Road bridge being demolished this morning (Sat). Perhaps they will move onto Colne Bridge while the line is closed. K
  5. S

    Transpennine Route Upgrade and Electrification updates

    Thankyou. Lots of interesting info RE the route and links to derailed drawings when you scroll down the document. One of the several Thornhill Road ones is below K :-...
  6. S

    Transpennine Route Upgrade and Electrification updates

    Great job searching through the jungle of planning documents which are supposed to be public. I tried unsuccessfully to find one of whatever there doing to the Thornhill Road bridge. K
  7. S

    Northern Ticket Machines

    As a senior I came to the conclusion a while back that you needed a degree to work them. Sadly I dont do trains much anymore. Fares a baffling. K
  8. S

    Transpennine Route Upgrade and Electrification updates

    Im surprised as one of the recent "On track with Tim" Youtubes clearly shows the trackbed of the new curve started. K
  9. S

    Transpennine Route Upgrade and Electrification updates

    Big weekend just passed. Looking at Sarah and Tims excellent Youtubes the A62 Leeds road bridge should have now reopened over the new span, workers where swarming over Huddersfield station and the fast lines trackbed was being excavated around Bradley so more rails soon perhaps. K
  10. S

    Transpennine Route Upgrade and Electrification updates

    Re Church Fenton station overbridge Common Lane. Looking at the TPE upgrade website it says Common lane bridge is to be closed to traffic July 26 to June 27 and replaced . Not seen any reports of progress or plans of the new structure. Anyone? I think this is the last bridge between York and...
  11. S

    Class 810 for East Midlands Railway Construction/Introduction Updates

    Watching the Green Signsls Youtube news channel it was mentioned "the 810s use the Italian AnsaldoBreda wiring system". AnsaldoBreda of course have form including the original Midland metro trams and troubles with train reliability actrss europe returned a whole batch of trains in Europe...
  12. S

    Discussion regarding electric train provision on newly electrified Transpennine Route

    All this talk of future services made me think after the wires are live to Hudds of all stops through emus between Huddersfield - York and Skipton - York. K
  13. S

    Transpennine Route Upgrade and Electrification updates

    Impressive progress indeed mostly shown on YouTube "On track with Tim" Anyone know the date for installation of the new track layout at Huddersfield? K
  14. S

    Discussion regarding electric train provision on newly electrified Transpennine Route

    Moderator note: Split from https://www.railforums.co.uk/threads/transpennine-route-upgrade-and-electrification-updates.88054 With past train procurements not going well, I'm beginning to doubt that Northern or TPE will have any new electric trains in time to use the new wires. K

Top