On this tender it has given these dates for HEX depot demolition, anyone know if these are still accurate?
Pre demolition surveys: as confirmed by the Local Authority and sub-contractor commencing in April 2021 Demolition and ground remediation: start June 2021. Completion of all works by...
Slough platform extensions for platforms 2,3,4 look complete. Platform 5 extension still on going.
Also perhaps some landscaping to complete between platform 3 and 4 extensions, and on the edge of platform 2.
Some further details on platform extensions and other station work here:
https://cdn.networkrail.co.uk/wp-content/uploads/2019/08/Crossrail-West-Stations-Newsletter-August-2019.pdf
“Work is scheduled to begin demolishing the sheds that are located within the Old Oak Common/Great Western Railway Compound, commencing on Monday 11 March 2019 for approximately eight weeks.”...
Reposting from the station designs thread, I’ll post everything to do with Old Oak Common here from now:
Old Oak Common Station design revealed
https://www.gov.uk/government/news/...gns-as-work-ramps-up-on-west-london-super-hub