Recent content by DirtyJohn

  1. D

    ScotRail HST Introduction - Updates & Discussion

    That would have slowed the production down. Once a vehicle has been stripped, it goes straight to the weld shop, and from the weld to the next station. That is usually the team who work on the underframe. Also in between stations there is sometimes arising work from previous stations. I...
  2. D

    ScotRail HST Introduction - Updates & Discussion

    It was getting shared, but the quality of work on the refurb side at kilmarnock was not upto scratch.
  3. D

    ScotRail HST Introduction - Updates & Discussion

    If i was a guessing man, i reckon all 26 sets could be done by december. Especially as a contact finishes in March which, would release a lot more welders and fitters/vehicle builders.
  4. D

    ScotRail HST Introduction - Updates & Discussion

    The asbestos was only minimal, it was found in the bitumen paint that was put on the inside shell when first built. It was classed as non licensed removal, and was removed in certain areas before it went to the welders and then vehicle builders. We are talking 0000000.1% but as we all know...
  5. D

    ScotRail HST Introduction - Updates & Discussion

    The first set started being stripped around September 2017, id like to know who said they could strip and build 26 sets in 1 year lol. There was issues at first with corrosion, asbestos, mold and workers leaving for Hitach. Even without those problems, there's no chance you're gonna get all...
  6. D

    ScotRail HST Introduction - Updates & Discussion

    Its all but confirmed that there will be some more GWR, maybe around 12 cars.
  7. D

    ScotRail HST Introduction - Updates & Discussion

    Set 12 is due to leave Friday, GWR is all but done and the XC will be around June time. There is another contract finishing in March, so that will give the ASR a big push.
  8. D

    ScotRail HST Introduction - Updates & Discussion

    By Easter that could well be the case, the GWR and another contract at Wabtec will finish. Those spare men will all move over to the ASR side, hopefully speeding things up.
  9. D

    ScotRail HST Introduction - Updates & Discussion

    Set 19 and most of 20 are all stripped, and moving along the stations. The next few sets are all close, with 16 being scheduled to leave for May time.
  10. D

    ScotRail HST Introduction - Updates & Discussion

    Around 12 sets have been stripped already.
  11. D

    ScotRail HST Introduction - Updates & Discussion

    Just the Scotrail sets. GWR and XC will be staying at Doncaster.
  12. D

    ScotRail HST Introduction - Updates & Discussion

    I think the Kilmarnock guys will be starting within the next 2 weeks.
  13. D

    ScotRail HST Introduction - Updates & Discussion

    Deadline for those two sets, not sure of the implications if they don't get them out.
  14. D

    ScotRail HST Introduction - Updates & Discussion

    You're right, 4 and 5 are the closest to being completed. 6 and 7 are being worked on, and 8 and 9 are all but stripped and ready for the next phase.
  15. D

    ScotRail HST Introduction - Updates & Discussion

    They need to be completed by the end of April.