• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Recent content by ATTERO_ATTERO

  1. A

    Platform extensions question

    Yes that's correct it is TVP is a track visitors permit but as I replied to the person below its just said PTS etc The question is for railway workers who will know because even the course is called PTS course
  2. A

    Platform extensions question

    Hi all I am going to try and make this short but I am hoping someone can settle a dispute I am having. I am a Controller of Site Safety (COSS) working on platform extensions, we have the operational side sectioned off to stop public whilst we are building the platform up. I have had a manager...
  3. A

    Headspan isolation

    Thanks Steve for your help. I was asking the AP the other day about the protection on RC wires and he said 9/10 you will not see line guards....that thought of well what if there is damage whos gonna cop it came into my mind because your the AP at the DEP and you have followed the correct...
  4. A

    Headspan isolation

    Hi all, I am in the process of learning how to be an AP whilst being out as the Earthing assistant. I have seen how cantilever isolation is done but so far I have not seen an AP carry out headspan. How is the isolation process carried out properly? where do the earths connect to? Thanks

Top