Is the platform going to be north or south of the road bridge? The car park is mentioned to the south, but I can't see any details for the platform itself.
The NorthIs the platform going to be north or south of the road bridge? The car park is mentioned to the south, but I can't see any details for the platform itself.
In the photo below the station is going to be where the marked location dot is in the centre of the photo. The red scribble opposite is the land allocated for the car park and is on the opposite side of the railway line on the south side.Is the platform going to be north or south of the road bridge? The car park is mentioned to the south, but I can't see any details for the platform itself.

Network Rail has released new aerial photos showing the first six months of progress on Okehampton Interchange station, which is set to open in 2026.
The station will be the newest addition to the Dartmoor Line, connecting West Devon, Torridge and North Cornwall with Exeter and beyond. The £15 million scheme is being funded by the Department for Transport (DfT) with contributions from Devon County Council and West Devon Borough Council.
Since work began in January, major progress has been made to create the new station on the edge of Okehampton, two minutes from the A30.
In March, 300 metres of the single-line track was moved 90cm north to allow a new platform to be built alongside it. The previous track layout didn’t allow for a platform to be built that meets regulations for new stations.
New track and 20 concrete sleepers were installed in the new alignment and 1,000 tonnes of ballast (track stone) laid and compacted. Drainage work also took place with two new chambers built under the track and 300 tonnes of stone laid to allow water to flow away from the railway.
Then in May, 25 bored piles were driven 12 metres into the ground to support the new platform, footbridge and lift.
The next major stage of work will see the footbridge and lift shaft installed in autumn. Work is also ongoing to build a 200-space car park and station platform.
Nice to see the progress being made. But I couldn't help notice this bit:Network Rail have put out a press release showing progress to date:
![]()
Pics: New Devon station takes shape after six months of progress
Network Rail has released new aerial photos showing the first six months of progress on Okehampton Interchange station, which is set to open in 2026.www.networkrailmediacentre.co.uk
NetworkRail said:In March, 300 metres of the single-line track was moved 90cm north to allow a new platform to be built alongside it. The previous track layout didn’t allow for a platform to be built that meets regulations for new stations.
See all the comments about “gold-plating” and project creep elsewhere relating to other things. Quite apart from the fact that the original reopening was in some ways a pilot exercise in “jfdi”, just imagine the reaction if £x had been spent slewing the track for a station that never got built because the passenger numbers didn’t stack up.Was it really impossible to anticipate that and make sure the track was laid in the correct location when they were first converting the line for regular passenger use? Would have made the whole project rather simpler/cheaper I would imagine.
Good progress with Okehampton Interchange.Nice to see the progress being made. But I couldn't help notice this bit:
Was it really impossible to anticipate that and make sure the track was laid in the correct location when they were first converting the line for regular passenger use? Would have made the whole project rather simpler/cheaper I would imagine.
Further rail improvement work is planned in the next few months affecting the following routes:
....
Exeter St Davids to Okehampton/Barnstaple – Saturday 21 to Sunday 29 March
Okehampton Interchange, the newest station in the region, is a big step closer to welcoming passengers after a major stage of construction was completed.
The lift shaft, footbridge span and staircase have all been lifted into place, with the station now beginning to take shape.
The new fully accessible station, being built by Network Rail and its contractor Octavius, is set to open in summer 2026.
I expect track engineers didn't know exactly where the new platform would be. There likely wasn't a detailed design for it yet. I expect there may have been station options that didn't move the track, but shifting it may still have been the best choice if alternatives incurred greater expense moving drainage, constructing larger retaining structures, etc.See all the comments about “gold-plating” and project creep elsewhere relating to other things. Quite apart from the fact that the original reopening was in some ways a pilot exercise in “jfdi”, just imagine the reaction if £x had been spent slewing the track for a station that never got built because the passenger numbers didn’t stack up.
Okehampton Interchange Station set to open this September
By Amy Hetherington | Reporter |
Thursday 22nd January 2026 11:54 am
amy.hetherington@okehampton-today.co.uk
The Okehampton Interchange Station, which is currently under construction, is due to open to the public this September after a trial period beginning in May.
From May, rail services will conduct trials to test how the system functions and ensure the safety of the building and infrastructure. This is the final phase before the station is officially opened. The new station will connect the east side of Okehampton and be an additional stop on the Dartmoor Line between Crediton and Okehampton’s existing station situated on the west side of the town.
The Government, Devon County Council, West Devon Borough Council, and Network Rail have all invested in the project, which has cost around £15 million.
Two photos from a train showing current progress with Okehampton Interchange.
View attachment 199918 View attachment 199919
Towards Okehampton. Towards Exeter.
Partners made a visit to Okehampton Interchange this week to see the latest progress in advance of the station’s opening this summer.
The interchange will provide easy access to those who are walking, cycling, or using local bus services with a train service to link West Devon and the surrounding areas to Exeter and beyond.
More details on the opening date to follow soon.
The diagram on the website suggests a more direct path from Summering Close (through the housing estate) to Kellands Lane then across the road to the station. On the other side the path is through the existing industrial estate. A couple new pedestrian crossings going in.I managed to get a couple of pictures of the platform from the industrial estate side, looking towards Exeter. One thing I'd like to know is how the station will be reached on foot, will a new path be laid from the main road, or are they expecting people to walk through the estate?
View attachment 202509
View attachment 202510
I don't know how good the train-bus connections are today, hopefully care will be taken to maintain or improve the timings at the new station. Given the low frequency of bus and rail services, it won't be a given that connections will line up.Okehampton Int.
Latest info. + video of Okehampton Interchange - looks pretty much complete, but no opening date announced yet. It will have to be co-ordinated with the move of all the bus services currently serving the existing station.
My brain definitely didn't read that as Okehampton International......
I`m told a unit is running to Okehampton Interchange one day next week to check platform hight clearances etc.
175's have made a couple of route proving runs lately, including stopping at Okehampton Interchange.So any further updates on opening? Have been to Okehampton several times recently and everything looks almost ready to go....
I was wondering if they were waiting for a 175 in GWR livery to do a big press event at the station but wasn't sure if 175 had been cleared on the line yet?
August has been mentioned couple of times, but not a specific dateSo any further updates on opening? Have been to Okehampton several times recently and everything looks almost ready to go....
I was wondering if they were waiting for a 175 in GWR livery to do a big press event at the station but wasn't sure if 175 had been cleared on the line yet?
Alleged by who, Karen on Facebook?It’s been alleged that this eagerly awaited and completed new railway station may not now be opened until
gWR Managers are confident that it will not be subject to the daily scourge of DMU failures, including the troublesome class 175 units, traincrew shortages ( 3 Exeter/ Okehampton services each way cancelled today 19/7/26) and general operational and infrastructure shortcomings.
It's different, trains run past it anyway, so no new trains, just an additional stopProbably the December timetable change. After all, what's a 6 month delay when a whole new line hasn't opened after 18 months....so far. (East-West)