East-West Rail (EWR): Consultation updates [not speculation]

Status
Not open for further replies.

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,593
Location
Nottingham
This is interesting as it suggests DfT require EWR to design build and operate the rolling stock and the services on the route. Obviously this will be after GBR has completed is takeover of the nascent TOCs - including Chiltern Trains which have yet to commence operation of Oxford - Milton Keynes Central. I assume EWR have signed a fixed term agreement with Chiltern Trains for ther initial period of operation.
The quote below doesn't necessarily imply EWR will be the operator. They are just progressing the track access and it will probably be for GBR to operate the actual service.
DfT has instructed EWR Co to design and deliver the required railway infrastructure for a 5-train per hour passenger service between Oxford and Cambridge. The Track Access Option (TAO) that EWR Co is progressing will therefore safeguard the capacity required to operate EWR services.
Also the linked document has a box ticked for "have [the services] operated on your behalf" noting
An operating company will be appointed by DfT to operate the services and as part of the appointment process it is expected that the operating company that is appointed will be duty holders that already hold safety certificates in line with ORR process.

  • although previous documents have proposed Cambridge-Stewartby trains, this is the first time I have seen Oxford-Stewartby, and this is likely to be linked to Universal, providing it with a service from the west even if it can't get into Bedford
It's also a bit odd that the train making fewer stops between Oxford and Stewartby is the one that terminates there. It makes more sense for this one to continue to Cambridge eventually as suggested as a possibility - but in this case would anything terminate at Stewartby and would it even require a third platform or turnback siding?
 
Last edited:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

cle

Established Member
Joined
17 Nov 2010
Messages
5,607
I would think that all 5tph should call at all of the new consolidated MV stations? Especially at 5 car.

Will the 2tph Bletchley terminators use the lower level platforms?

Seems to be a move here to kill of any XC / OA / other types of service. But I don’t mind a metro style service, it’ll see much more uptake.

The Stewartby easement is interesting as it really won’t see much at Bedford. This doesn’t require as much terminating infrastructure at Bedford at all.
 

eastdyke

Established Member
Joined
25 Jan 2010
Messages
2,058
Location
East Midlands
It's also a bit odd that the train making fewer stops between Oxford and Stewartby is the one that terminates there. It makes more sense for this one to continue to Cambridge eventually as suggested as a possibility - but in this case would anything terminate at Stewartby and would it even require a third platform or turnback siding?
I agree re 'fewer stops', it is odd.
Perhaps the idea of terminators at Stewartby has an element of contingency?
If 'The Park' opens for visitors in 2031 [and for workers before that]. It won't be a phased opening it will be the full job.

Can we really get Bletchley-Cambridge EWR fully up and running for 2031 - discuss!
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,630
Seems to be a move here to kill of any XC / OA / other types of service. But I don’t mind a metro style service, it’ll see much more uptake.
I don't see why, unless they are cutting it to the bone so much you can't physically timetable them. I would be very surprised if its built on worse than a 4 minute signalling headway.
 

Dr Hoo

Established Member
Joined
10 Nov 2015
Messages
5,604
Location
Hope Valley
Has the DfT/Secretary of State specified any capacity for freight (east of Bletchley) as part of this consultation update? Were the freight operators even consulted or just local bodies for this round?
 

Trainbike46

Established Member
Joined
18 Sep 2021
Messages
4,361
Location
belfast
Has the DfT/Secretary of State specified any capacity for freight (east of Bletchley) as part of this consultation update? Were the freight operators even consulted or just local bodies for this round?
The diagram includes 1tph for freight throughout
 

D365

Veteran Member
Joined
29 Jun 2012
Messages
13,157
Can we really get Bletchley-Cambridge EWR fully up and running for 2031 - discuss!
This is why I asked earlier about the possibility of an interim Oxford-Bletchley-Stewartby(-Bedford) service. That assumes though that Stewartby station will be ready in time!
 

cle

Established Member
Joined
17 Nov 2010
Messages
5,607
I don't see why, unless they are cutting it to the bone so much you can't physically timetable them. I would be very surprised if its built on worse than a 4 minute signalling headway.
I guess it depends which part, and also only 1tph for freight seems low. It’s very useful there.

If Chiltern add 2tph west of Bicester, that’s 8tph total through there (and a flat junction move) - so might be getting towards capacity?

I don’t see any long distance services not using the Oxford-Bletchley stretch.

Marston will be lower capacity signalled for sure.

Tempsford - no link to ECML.

And I don’t see other uses for the Bedford - Cambridge leg beyond EWR services and maybe some freight. Like Thameslink or MML to Cambridge?!

Amazing Bed-Cam releases something from Ely in terms of freight, but yes - in that direction both Ely and Stansted are full so it’s capped beyond Cambridge (East). I think North could have more platforms built though.


TLDR: the only realistic options for other services are (West)/Oxford to WCML or (West)/Oxford to MML. And Oxford-Bicester seems full?

Not counting Aylesbury in all this. That probably needs the 5th line and a platform added at MKC.
 

eastdyke

Established Member
Joined
25 Jan 2010
Messages
2,058
Location
East Midlands
Has the DfT/Secretary of State specified any capacity for freight (east of Bletchley) as part of this consultation update? Were the freight operators even consulted or just local bodies for this round?
The detailed Track Access Application at post #6594 has some info. The 'Application' was signed 12th December. The 'Industry Consultation' [ie not public] started 15th December and goes to a date [I havn't relocated yet!] in January.

It also includes some revealing [to me!] details of passing loops at various locations see here:

From section 8 Enhancement: [Large quote]
The proposed enhancements include:
• In and around Oxford station, we are reviewing what changes and new facilities might be
needed to enable five EWR trains per hour to serve Oxford station, to benefit passengers and
complement other projects already planned in the area.
• At Oxford Parkway, Bicester Village, Winslow, and Bletchley stations we are reviewing what
changes to the stations and parking facilities might be needed to benefit passengers.
• At Islip, we are proposing to construct a passing loop so that faster passenger services
heading towards Oxford can pass by slower trains including freight without delay, improving
the efficiency and punctuality of EWR services.
• At the London Road level crossing in Bicester, we are considering options for an alternative
accessible crossing including footbridge, lift and underpass options.
• At Middle Claydon, we are proposing to construct a passing loop so that faster passenger
services heading towards Oxford can pass by slower freight trains without delay.
to make the appropriate adjustments to services and Track Access Contracts to ensure capacity along
the new EWR line is fully optimised and aligned with the TAO. The rights transfer will take place before
service commencement and any amendments to the Schedule 8 clauses in those contracts will be
made as part of the transfer process.
• At Bletchley we are proposing a new accessible footbridge at the south end of the station,
with lifts and stairs to all platforms; Extended platforms and improved emergency exits for
platforms 6, 7 and 8; An expanded western ticket hall and gate line, along with upgrades to
the station forecourt. In addition to these improvements, we’re now considering including an
eastern entrance to the station within our design, although the construction of this entrance
would be subject to securing third-party funding.
• Between Fenny Stratford and Kempston, we are proposing to upgrade the stations and
train services on the Marston Vale Line. Taking account of feedback from previous
consultation and ongoing engagement with local stakeholders has led to a decision to move
forward with the Consolidated Stations Option. This replaces the existing nine stations with
four new, larger, easy to access stations at Woburn Sands, Ridgmont, Lidlington and
Stewartby along with the relocated Bedford St Johns. Further information about this approach
can be found here: EWR-YSWD-Autumn-Update-2025-FOR-SCREEN-v2.pdf
• We will upgrade the railway tracks where needed to allow for new EWR services, including
building a second track between Bletchley station and where the railway crosses the A5
before Caldecotte.
• Make changes to the level crossings in this area, including diversions and closing some
crossings.
• Construct passing loops to allow faster trains to overtake slower trains including freight,
allowing passenger train journeys to be quicker.
• Relocating Bedford St Johns station to the west to better serve Bedford Hospital and to
improve the alignment of the railway into Bedford station so that trains can travel at the speeds
required to run the proposed EWR timetable.
• Building a new two-track railway to the north of Sandhurst Road that would replace the
existing single track Marston Vale Line into Bedford station – again to help achieve the EWR
timetable.
• We are moving Jowett sidings to Cauldwell Walk, making space for the railway tracks as they
approach Bedford station.
• At Bedford station, we are considering a range of work including rebuilding the station
building, creating a new station plaza, constructing footbridges and two new platforms and
providing replacement car parking, all to give passengers the best possible experience. In
addition, we are considering the introduction of an up-fast platform which would improve
interchange between train services east and west as well as north and south, as well as a
new western entrance to the station.
• North of Bedford, we are planning to construct an additional two tracks alongside the Midland
Main Line to make sure EWR services can run reliably without conflicting with other trains.
We are also proposing to construct a new 1.1km long viaduct over the River Great Ouse and
Paula Radcliffe Way.
• We are planning to lay approximately 12km (7 miles) of new railway track between Clapham
Green and Colesden, and build embankments, cuttings, bridges and viaducts where needed
to enable this.
• Near Colesden, we are proposing to install two passing loops so that faster passenger trains
could overtake slower trains, including freight.
• Between Roxton and east of St Neots, we are planning to construct a section of twin-track
railway and associated infrastructure approximately 10km (6 miles) long. As part of the 2023
route update announcement we confirmed that Alignment 1 (Tempsford variant) was the
preferred alignment for the route between Bedford and Cambridge. This alignment would
serve a new station at Tempsford. Since then, we have developed two local variations,
Alignment 1b and Alignment 1c, each making use of viaducts linked by embankment.
Alignment 1b has been developed from the route update announcement proposals and runs
south of the A421. Alignment 1c is an alternative running north of the A421 with connections
to the south. Taking account of the consultation feedback and the outcome of further
assessments and design development, we’ve selected Alignment 1c as the proposed
alignment.
• At Tempsford, we are proposing a new station to serve existing and future communities which
would also include an interchange with the East Coast Main Line to enable travel further
afield. As the station design is progressed it will include consideration of existing communities
as well as planned and potential development within the area.
• Between Croxton and Toft, we are planning to construct approximately 19km (12 miles) of
twin-track railway including passing loops, to enable travel by railway from Bedford to
Cambridge.
• At Cambourne, we are planning to build a new station to improve connectivity into Cambridge
for people living there and support the future growth of the town.
• To reduce the environmental impact of the railway, we propose constructing a mined tunnel
beneath the A428, the proposed Bourn Airfield development and Highfields Road, with an
associated temporary diversion of the A428 and other local roads.
• Between Comberton and Shelford, we are planning to construct two new tracks between
Comberton and Hauxton Junction east of the A10 Royston Road where they would join the
existing railway.
• We are proposing the construction of a tunnel, bridges and crossings so that roads and
footpaths can cross the railway including the A10 Royston Road diversion.
• At the Harston level crossing, we are looking at options for how we can avoid separating the
communities of Harston and Newton when the level crossing is closed, so that the connection
between the villages can be maintained.
• We are considering what changes would be needed to the Hauxton Royston Line and West
Anglia Main Line to allow them to connect with East West Rail and to reduce possible
disruption on the railway.
• At Hauxton Junction, we are planning the construction of passing loops to allow fast trains to
overtake slower trains, including freight, to help avoid any delays.
• In the Cambridge area, to make sure there are enough railway tracks to accommodate the
new EWR services, we are planning to lay two new railway tracks next to the existing two-
track West Anglia Main Line on its western side from Addenbrooke’s Road. These would join
the existing four tracks at the new Cambridge South station (currently being constructed by
Network Rail), and continue into Cambridge station.
• We are proposing to demolish the overbridge at Long Road and provide a new bridge wide
enough to fit the railway underneath.
• At Cambridge station, we are planning a new platform, platform extensions, bridges, building
upgrades and railway systems modifications – all to give passengers the best possible
experience.
• At the existing level crossing at Laundry Lane, we are planning safety improvements that are
needed as a result of the planned increase in train speeds and the addition of a track in this
area.
• At Cherry Hinton, we are proposing a new train turnback facility so that EWR passengers can
alight at Cambridge station and trains can continue to Cherry Hinton to turn around. This
would avoid the need for trains to turn around at Cambridge where there is currently
insufficient platform capacity to accommodate both existing and new EWR services.
• We are planning to reconstruct two footbridges at Coldham’s Common and The Tins footpath
to allow for electrification of the railway and the addition of a second track.
• We are considering where to locate two railway sidings that will be lost due to the proposed
works at Cambridge station. The two emerging possible locations for these are Chesterton
sidings at Cambridge North station.
• At Cambridge North station, we are planning to modify the track layout to allow for some
existing train services from the north to terminate there during our construction works at
Cambridge station.
• There will also be new depot facilities required, and these sites are subject to ongoing
development and consultation.
 
Last edited:

Magdalia

Established Member
Joined
1 Jan 2022
Messages
7,300
Location
The Fens
The detailed Track Access Application at post #6594 has some info.
Thanks for this. Most is what would be expected from the 2024 consultation and the You Said We Did report.

in this case would anything terminate at Stewartby and would it even require a third platform or turnback siding?
The You Said We Did report has this for Stewartby:

Taking account of consultation feedback, we continued to work on our designs for the Stewartby station options, including proposals for how people can use active travel to reach local destinations from the station. We undertook a careful comparison of the two station options to consider the relative advantages and disadvantages of each. Based on this work and taking account of consultation feedback, we concluded that a new Stewartby-Kempston Hardwick station would best be located north of Broadmead Road (Option 2) as:

  • The location of Option 2 further north aligns with Bedford Borough Council’s Local Plan 2040, which sets out aspirations for new housing and businesses in the surrounding area.
  • The land that would be needed for Option 1 already has planning consent for development and this means it would carry a high land price. In contrast, the land needed for Option 2 would offer better value for taxpayers.
  • Option 2 avoids significant impacts on the development of the Stewartby Brickworks site (which is near to the location for Option 1).
  • Option 2 offers better integration with the local road network, making it easier to access the station.
  • Bedford Borough Council, the Local Planning Authority for Stewartby station, have expressed support for Option 2.
Since this exercise, Universal’s proposals for a resort in this area have also progressed and now, taking these into account, we believe the case for this relocation is even stronger given the opportunities to support sustainable travel to and from this international destination.

Given Universal’s proposals are still emerging, we’re working with them and other stakeholders to determine the design and exact position of the station. We would like to provide reassurance that as we progress this work, we are focused on not just integrating the design for this station with the wider development proposals but also maintaining access to the strategic road network and local destinations including Kimberley Sixth Form College and Stewartby.

I think North could have more platforms built though.
I guess you mean Cambridge North here? EWR have said very little about Cambridge North until now, but the Track Access Application has these that I have mot seen before:

• We are considering where to locate two railway sidings that will be lost due to the proposed
works at Cambridge station. The two emerging possible locations for these are Chesterton
sidings at Cambridge North station.
• At Cambridge North station, we are planning to modify the track layout to allow for some
existing train services from the north to terminate there during our construction works at
Cambridge station.

The proposal to build in capability to reverse at Cambridge North from the Ely direction is especially welcome as the the work at Cambridge will require a lot of closures.
 

Dr Hoo

Established Member
Joined
10 Nov 2015
Messages
5,604
Location
Hope Valley
Thanks to @eastdyke for attaching that excellent description of the work envisaged, including looping facilities for freight. So, a Class 6, 60-mph diesel-hauled stone train from the Mendips to Wast Anglia (for example) might ‘hop’ from loop to loop in between a roughly quarter-hourly passenger service with few stops on many sections and a 90/100-mph potential maximum speed.
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
The proposal to build in capability to reverse at Cambridge North from the Ely direction is especially welcome as the the work at Cambridge will require a lot of closures.
That is already possible and is being used with the 2025 Christmas Closures for Cambridge Resignalling.

Sadly no mention of Claydon Junction to Aylesbury. Is that dead ?
HS2 has to put that back. Not dead yet and it should be pointed out that the diagram in @Verulamius post above has two terminators at Bletchley from Cambridge that leaves options open.
 

Magdalia

Established Member
Joined
1 Jan 2022
Messages
7,300
Location
The Fens
That is already possible and is being used with the 2025 Christmas Closures for Cambridge Resignalling.
It is possible, but severely restricted, as today's timetable demonstrates. Only platform 2 at Cambridge North is directly reversible from the Ely direction, and that's what the Kings Lynn trains are doing. On the other hand the Norwich trains are having to arrive in platform 1, wait for the Kings Lynn train to arrive and depart, and only then shunt to platform 2. I'm guessing that Fen Road level crossing barriers have to go down for this.

Modifying the track layout to also allow reversals in platforms 1 and/or 3 from the Ely direction will provide more capacity, and remove the need to shunt over Fen Road level crossing.
 

Steve Harris

Member
Joined
11 Dec 2016
Messages
1,193
Location
ECML
The detailed Track Access Application at post #6594 has some info. The 'Application' was signed 12th December. The 'Industry Consultation' [ie not public] started 15th December and goes to a date [I havn't relocated yet!] in January.

It also includes some revealing [to me!] details of passing loops at various locations see here:

From section 8 Enhancement: [Large quote]
It's 12/01/26 (it's literally on the right of the start date in section 1.6 of the document).
 

cle

Established Member
Joined
17 Nov 2010
Messages
5,607
HS2 has to put that back. Not dead yet and it should be pointed out that the diagram in @Verulamius post above has two terminators at Bletchley from Cambridge that leaves options open.
It seems received wisdom that an Aylesbury service (or a first one) would run to MKC. I can’t see as much demand for onwards towards Bedford. Unless modelling shows Bletchley is sufficient? I doubt it though, for jobs access.
 

D365

Veteran Member
Joined
29 Jun 2012
Messages
13,157
Cambridge terminators would presumably run into the Bletchley low-level platforms rather than occupying the high-level platforms.

The issue with Aylesbury services will be the lack of electrification as things stand.
 

PLY2AYS

Member
Joined
26 Mar 2024
Messages
518
Location
Montserrat
With the proposed BEMU fleet, yes. Unless DMUs or MMUs are used instead.
I haven’t seen anything about a BEMU tender or any electrification in/around Oxford; have you got a link?
Or if it’s just a proposal at this point, any references to it, would be good reading!
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,630
Cambridge terminators would presumably run into the Bletchley low-level platforms rather than occupying the high-level platforms.

The issue with Aylesbury services will be the lack of electrification as things stand.
Why? It depends on who runs them or how it works. If its BEMU, the run between Denbigh Hall and MK and any turnaround time could well be enough for what is a relatively short journey.
 

Magdalia

Established Member
Joined
1 Jan 2022
Messages
7,300
Location
The Fens
Businesses in the Oxford Cambridge Corridor are starting to get impatient about rate of progress on East West Rail see here:


Industry leaders have called for the construction of the new railway line linking Oxford and Cambridge to be fast-tracked.

Several businesses have urged the government to start work on the East West Rail (EWR) during this Parliament, which aims to create a "crown jewel" of European science and innovation in the sub-region.

EWR would create a new direct railway line between the two university cities, via Milton Keynes and Bedford.

However, businesses are concerned that the development consent order (DCO) - which lets the government build infrastructure - is not due to be submitted until 2027.

The report by the Oxford-Cambridge Supercluster Board, external has urged Chancellor Rachel Reeves to move more quickly to propel growth in the so-called "high-tech corridor" by speeding up the building of infrastructure and homes.

The board is backed by 46 organisations including universities, listed companies, and global investors such as AstraZeneca, GSK, Airbus, the Ellison Institute of Technology, Aveva, Bidwells, Leonardo, Silverstone and Darktrace.

Starting construction in this five-year Parliament would provide the certainty investors needed, said the report.

Firms are worried it will take 18 months for the DCO to be approved.

I had not heard of the Supercluster Board before. It has a website here:


Welcome to the Oxford-Cambridge Supercluster Board, where industry leaders, universities, and investors come together to drive innovation, unlock investment, and shape policies to propel the UK towards its Science Superpower ambition.
 

djox

Member
Joined
25 Jan 2025
Messages
77
Location
Oxford
Businesses in the Oxford Cambridge Corridor are starting to get impatient about rate of progress on East West Rail see here:






I had not heard of the Supercluster Board before. It has a website here:

The BBC article is a bit pathetic, it's like the reporter doesn't even know that the line from Oxford to Beckley/MK is built and ready to use.
 

Mikey C

Established Member
Joined
11 Feb 2013
Messages
8,231
The BBC article is a bit pathetic, it's like the reporter doesn't even know that the line from Oxford to Beckley/MK is built and ready to use.
Does the government know the Oxford to Bletchley line is built, as its opening date is drifting ridiculously...
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,235
A short video from EWR on the recent ground surveys for the replacement of the single track bridge over Saxon Street (V7) in MK:

The video also includes some renders of the proposed new bridge.
 

al green

Member
Joined
2 Oct 2011
Messages
159
A short video from EWR on the recent ground surveys for the replacement of the single track bridge over Saxon Street (V7) in MK:

The video also includes some renders of the proposed new bridge.
The road closure caused chaos in Bletchley and Fenny Stratford for the whole week. Buses were diverted but the diversion route was so congested that it had to be abandoned aFter a couple of days. Most Buses had to miss out Bletchley bus station and a shuttle bus was provided to link Bletchley bus station to Fenny Stratford, which was on the second diversion route. Sadly there was no communication with passengers about these late changes, not on MKCC or Arriva websites, nor any posters in Bletchley bus station. The driver of the shuttle bus had to speak to each waiting passenger at Bletchley bus station and convince them that they needed get on his bus. Some were reluctant. because the real time info was still telling that their bus was due shortly, even though in reality it was not going there at all.

When the rebuild of the flyover takes place and the road is closed for several months the bus diversions must be handled much better.
 