Christmas 2025 isn't it, was re-announced in the Budget "Church Fenton" to York will be completed in early 2026.
"further electrification of services between Church Fenton and York by 2026" presumably means just adding the wires to bridge the gap at Colton Junction.
 

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,173
Location
West Yorkshire / Birmingham
It’s already wired and trains have been tested in OHL
I think it would be reasonable to assume that they’re just waiting for the rest of the wiring to Cross Gates to be completed in Spring 2026, delayed from Christmas 2025 to put the wires into service. Until then the wires between Church Fenton and Colton Junction will remain live to deter theft.

It does seem like an astonishingly long time considering that most of the wiring was done by summer 2022.
 

Nottingham59

Established Member
Joined
10 Dec 2019
Messages
3,326
Location
Nottingham
It’s already wired and trains have been tested in OHL
A post upthread suggests that, despite the OHLE being energised, there is still some wiring work to be done at Colton junction.
According to the May issue of Modern Railways, summarised by me in #7868, in this case initial energisation comes before the final reconfiguration of the wires at Colton Junction. It seems a bit odd to me but I assume they know what they're doing. Presumably it enables them to fully test the wires, except for the immediate Colton area, in advance of final completion, which will probably require an ECML possession. Also deters theft.
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,661
I think it would be reasonable to assume that they’re just waiting for the rest of the wiring to Cross Gates to be completed in Spring 2026, delayed from Christmas 2025 to put the wires into service. Until then the wires between Church Fenton and Colton Junction will remain live to deter theft.

It does seem like an astonishingly long time considering that most of the wiring was done by summer 2022.
I wasn't aware cross gates by early 2026 was the official target. Lot of work to do in 2025 to achieve that including around Church Fenton station itself.

If it is 2026 it will be a great shame to then wait a number of years for Neville Hill to allow it to link up!
 

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,173
Location
West Yorkshire / Birmingham
I wasn't aware cross gates by early 2026 was the official target. Lot of work to do in 2025 to achieve that including around Church Fenton station itself.

If it is 2026 it will be a great shame to then wait a number of years for Neville Hill to allow it to link up!
This date was mentioned in this video, which came out 6 months ago.


Skip to 13:10 to see the talk about timeframes.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,455
Location
Preston Lancs
I wasn't aware cross gates by early 2026 was the official target. Lot of work to do in 2025 to achieve that including around Church Fenton station itself.

If it is 2026 it will be a great shame to then wait a number of years for Neville Hill to allow it to link up!
I am happy that it is getting done - even if it will be ages before full completion.
 

Cletus

Established Member
Joined
11 Dec 2010
Messages
2,395
Location
Dover
Sorry doesn't seem to allow pdf files. The Sarah bell video linked on recent post 8660 shows it better.
K

== Doublepost prevention - post automatically merged: ==

Another excellent Youtube from Sara Bell showing current works at Mirfield and Heaton lodge. At Mirfield Sta the road under is to be temp closed ro allow the steps up to the platform to be enlarged and modernised.
Work at Mirfiekd seems tk have been going on for a long time now.
See
K
Sarah Bell’s videos are very good visuals of what is going on. Better than what I’ve been reading on this thread tbh.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,983
Location
Surrey
The 802s no longer change power modes at York station but by the Park and Ride facility on the outskirts of York. That does give the train enough time to reach the current linespeed of 100mph on electric.
Thanks for clarity so if they can do out there should just be matter of moving the kit down towards Church Fenton now. Also whats happening down at the Staylbridge end?
 

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,173
Location
West Yorkshire / Birmingham
Thanks for clarity so if they can do out there should just be matter of moving the kit down towards Church Fenton now. Also whats happening down at the Staylbridge end?
The 802s have started using the OLE, although when I was on one the other day it still left Stalybridge on diesel and only put its pantograph up partway between Ashton-under-Lyne and Miles Platting.
 

John R

Established Member
Joined
1 Jul 2013
Messages
6,061
Thanks for clarity so if they can do out there should just be matter of moving the kit down towards Church Fenton now. Also whats happening down at the Staylbridge end?
Post #8675 suggests that isn’t the case, as the configuration at Colton is not complete despite the wires having been energised.
 

InOban

On Moderation
Joined
12 Mar 2017
Messages
4,537
But presumably the issues at Colton Junction would affect only the ECML and Normanton line and would/might not affect the Leeds lines?
 

Richard123

Member
Joined
11 Nov 2018
Messages
110
Location
Rugby
Post #8675 suggests that isn’t the case, as the configuration at Colton is not complete despite the wires having been energised.
Complete, but to be modified to tangential running for higher reliability at 125mph in the future I believe.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
Clayton Bridge
Which was the location mentioned in post #8599 3 weeks ago, the discussion then meandered off towards Askham Bar, and eventually returned to the west. AIUI any APCO location has to be a significant distance from the end of the wires, to allow room for the manual procedure if auto fails?

== Doublepost prevention - post automatically merged: ==


What is tangential running, please?

I tried to explain here:


…but it’s probably best to follow the link to the drawings in Garry Keenor’s electrification guide.
 

Tim_UK

Member
Joined
9 Jan 2019
Messages
223
In Huddersfield.
There are a load of concrete bridge sections on trucks in the old technical college card park, next to New North Road. They were there on Thursday and still there today. I'm not sure where they are for, but they are clearly labelled Transpennine Route Upgrade in a giant banner.
(sorry, not had a camera or I've been driving)
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,856
Location
west yorkshire
Another excellent Sarah Bell video showing the christmas bridge work at Neville hill as well as progress with mast planting east of Micklefield and between Cottingley and Mörley.
Interestingly some of the single mast arms look much like the great western ones. See:-
K
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,455
Location
Preston Lancs
I took a trip to York today. Not much further to report though the beer in the Tap Room on York station is fantastic. Progress everywhere except Stalybridge to Huddersfield. Loads of masts and compounds Especially this beaut at Huddersfield. IMG_0986.jpeg
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
Don't suppose anyone knows what the timeline is for each part of the Transpennine Upgrade? I'd like to make a table showing this on the Wikipedia page (so will need references!)
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,455
Location
Preston Lancs
Don't suppose anyone knows what the timeline is for each part of the Transpennine Upgrade? I'd like to make a table showing this on the Wikipedia page (so will need references!)
I will see what I can do. However, there has been a change in government as you know in the last 6 months so I suggest waiting until March when the chancellor and Secretary of State give an update.
 
Last edited:

nr758123

Member
Joined
3 Jun 2014
Messages
636
Location
West Yorkshire
Don't suppose anyone knows what the timeline is for each part of the Transpennine Upgrade? I'd like to make a table showing this on the Wikipedia page (so will need references!)

The agenda papers for the Rail North Committee of 3rd September 2024 include a "State of Play" gantt chart. Item 5, Appendix 1. Link is RNC 030924. Others will be better qualified than me to assess how realistic this is. One thing I noted was that TRU Marsden to Huddersfield does not appear on the chart at all.
 

Roast Veg

Established Member
Joined
28 Oct 2016
Messages
2,319
Thornhill Road, just south of Dewsbury station, has digital signs up promising a closure from January to June 2025. This is immediately adjacent to the TRU compound there.
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,587
The agenda papers for the Rail North Committee of 3rd September 2024 include a "State of Play" gantt chart. Item 5, Appendix 1. Link is RNC 030924. Others will be better qualified than me to assess how realistic this is. One thing I noted was that TRU Marsden to Huddersfield does not appear on the chart at all.
Thanks! I've added this to the Wikipedia article - agree it's weird that Marsden to Huddersfield doesn't feature!
 