Transpennine Route Upgrade and Electrification updates

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,452
Location
Preston Lancs
The site teams must have been taking advantage of the extended blockades by doing this instead of piles, although I'm sure the ground conditions would have had some bearing on the types of foundation chosen.
No doubt about it imho. Surely there will be some ancient mining activity in the area so it makes sense.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

modernrail

Established Member
Joined
26 Jul 2015
Messages
1,440
Quite something to finally see some signs of electrification on the core of the most important intercity line in the country!!!

What is the planned switch on date?
 
Joined
5 Aug 2015
Messages
868
Location
Norfolk
They have on some other schemes. There doesn't seem to be any consistent practice - what is done for Stalybridge and Church Fenton? I assumed GFL is some extrapolation of the system that was defined back in the 50s - G is WCML so it may be treated as a branch of a branch off that.
yeah I considered that too but it'd make more sense in that location to play off ECML's "E". Especially since Manchester Picc to Crewe is "M".
+
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,586
Location
Nottingham
yeah I considered that too but it'd make more sense in that location to play off ECML's "E". Especially since Manchester Picc to Crewe is "M".
+
Perhaps whoever allocated this has a sense of history, as it's an ex-LNWR route which was connected to the rest of their network via Stockport-Stalybridge.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,978
Location
Surrey
Update from one of the site engineers from the ongoing blockade. It sounds like lots of steelwork to be installed next.


Photos with link
Thats excellent rate of installation and on a par with what was being on ECML nigh on 40yrs ago. It demonstrates whats achievable when the contractors are let off the leash and shows lines could be electrified alot quicker and thus cheaper with the right approach.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,452
Location
Preston Lancs
Thats excellent rate of installation and on a par with what was being on ECML nigh on 40yrs ago. It demonstrates whats achievable when the contractors are let off the leash and shows lines could be electrified alot quicker and thus cheaper with the right approach.
Indeed. I really am beginning to feel a lot more optimistic.
 

L+Y

Member
Joined
4 Jul 2011
Messages
501
With masts now going up and layouts being "locked in", has a decision been taken on whether or not to reinstate four tracking in the Cross Gates area?
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,661
Do we know how much the TRU electrification is costing, and whether it has actually achieved the cost savings hoped for?
I think both sides of the electrification arguement will use TRU to further their case. TRU is not an electrification project it is a route upgrade project and I suspect separating costs will be a dark art hence being able to manipulate that to further their cause.

On a separate point, on my travels to work today the piles are definitely spreading from the Garforth compound. It looks like all the easy (easy being relative) piles are going in, with gaps around some harder areas such as tight rock cuttings.

Progress being made at Church Fenton, with the route of the new road now visible and material being compacted in layers.
 
Last edited:

superkev

Established Member
Joined
1 Mar 2015
Messages
2,856
Location
west yorkshire
I seem to remember the original scheme included Micklefield jnc to Hambleton jnc and Selby fro cross Leeds electrics but these we're Graylinged (paused).
The few miles to Hambleton would be a usefull diversionary route.
Has it been reinstated?
K
 

3RDGEN

Member
Joined
6 Mar 2023
Messages
583
Location
Hull
I seem to remember the original scheme included Micklefield jnc to Hambleton jnc and Selby fro cross Leeds electrics but these we're Graylinged (paused).
The few miles to Hambleton would be a usefull diversionary route.
Has it been reinstated?
K
Not as part of TRU, it's Leeds - Church Fenton only.

Micklefield to Hull was mentioned in the Network North proposals but that is all up in the air for now, however;
https://www.hulldailymail.co.uk/new...nsport-secretary-hull-sheffield-leeds-9478243 -

'Be in no doubt, Diana Johnson lobbies me on it every day'

"Transport Secretary Louise Haigh has stopped short of a firm commitment to the electrification of the Hull to Sheffield and Leeds rail lines.

…asked if the new government was committed to the electrification of the lines. Ms Haigh indicated there is a review of ongoing and committed infrastructure projects made by the previous Conservative government.

Announcements will be made in the budget in October and comprehensive spending review in spring. While she did not commit to the lines' electrification, the Transport Secretary did state connectivity across the north of England was the only major infrastructure commitment made by Labour in its manifesto."
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,856
Location
west yorkshire
Not as part of TRU, it's Leeds - Church Fenton only.

Micklefield to Hull was mentioned in the Network North proposals but that is all up in the air for now, however;
Didnt Hull trains once offer to pay for wires from the ecml to Hull. They were turned down so had to buy Hitachi bi-modes.
K
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,571
Didnt Hull trains once offer to pay for wires from the ecml to Hull. They were turned down so had to buy Hitachi bi-modes.
K

They did, in return (IIRC) for a long access contract.

I also guess that as with almost every other TOC or local authority who tries their hand at major rail infrastructure work, they would have underestimated the complexity and therefore cost. But that’s my personal opinion.
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,276
They did, in return (IIRC) for a long access contract.

I also guess that as with almost every other TOC or local authority who tries their hand at major rail infrastructure work, they would have underestimated the complexity and therefore cost. But that’s my personal opinion.
I thought the sticking point was how much they wanted to charge for other companies using the wires???
 

grdc

Member
Joined
19 Feb 2023
Messages
30
Location
Morley
Went for another walk on Sunday 17/11/24 to check what had changed.

Walked down the footpath from Gelderd Rd towards the Ring Road bridge, nothing to see.

View towards Ring Rd/Leeds from the Gelderd Rd bridge:

mly01.jpg
mly02.jpg
View towards the M621/Cottingley from Gelderd Rd Bridge:
mly03.jpg
Vmly04.jpg
View from Cottingley Station footbridge, first larger 6 pin piles either side of bridge, then view towards White Rose station:
mly05.jpg
mly06.jpg
mly07.jpg
mly08.JPG
There were no piles on the Leeds side of the Cottingley footbridge or in/behind Cottingley station, or visible between the end of Cottingley's platforms and the M621.
Now the view from either side of Churwell Viaduct of White Rose station, showing the ladder style masts on both sides of the station, and a lone tubular mast with (shorter) jib/beam at the Morley side of the viaduct on the Leeds-Bound line:
mly09.jpg

== Doublepost prevention - post automatically merged: ==

mly10.JPG
mly11.jpg
mly12.jpg
View from Broad Oaks Farm, looking northwards towards Leeds and the White Rose station:

mly13.JPG
Note the three different mast types in this run, I'm calling them skinny I beam, fat I beam and ladder in absence of the correct terminology!
mly14.jpg
mly15.jpg
Next three pictures from taken on the opposite (northern) side of the line:

mly16.jpg
mly17.jpg
mly18.jpg
The mast above is between the White Rose centre network access gate, and the White Rose station site. I pushed as far as I could, but the footpath naturally becomes massively overgrown as it is fenced off by the arch tunnel at the station site and has therefore seen no foot traffic for years.
This style of mast, without its beam is present at either side of the White Rose centre footbridge:

== Doublepost prevention - post automatically merged: ==

mly19.jpg
mly20.jpg
mly21.jpg
We now look towards Morley/Huddersfield from the White Rose centre footbrige:
mly22.jpg
Note the same tubular mast, but with a longer Jib and no pile opposite suggesting it will carry both lines catenaries, with the odd "skinny I-beam" mast between them.
mly23.jpg
Close-ups of the tubular style mast and adjustable height jib in a medium length:
mly24.jpg
mly25.jpg
View from just above the new Daisy Hill Network Rail access gate towards the Natasha Elliot footbridge:
mly26.jpg
And the reverse view back towards the Daisy Hill gate:
mly27.jpg

== Doublepost prevention - post automatically merged: ==

Notice, two different sizes of I-beam, in different orientations. Wild how many different types of parts there are in this scheme.mly28.jpg


View towards Morley station from the Natasha Elliot footbrige, showing the last mast on this run, another tubular one with the shortest version of the jib attached:
mly29.jpg
mly30.jpg
mly31.jpg
The piles above, with boards on top appear to be the last they had done at this point, with none in/behind Morley station as per Cottingley presumably as suggested they are doing the easiest piles first:
mly32.jpg

As others have noted, they have made great progress during this blockade, its really exciting to see it all coming together.

This week Monday - Friday is the final blockade in the run, so will have another wander next weekend to see what's changed.
 
Last edited:

Halish Railway

Established Member
Joined
26 Apr 2017
Messages
2,173
Location
West Yorkshire / Birmingham
Went for another walk on Sunday 17/11/24 to check what had changed.

Walked down the footpath from Gelderd Rd towards the Ring Road bridge, nothing to see.

View towards Ring Rd/Leeds from the Gelderd Rd bridge:

View attachment 169485
View attachment 169486
View towards the M621/Cottingley from Gelderd Rd Bridge:
View attachment 169487
VView attachment 169488
View from Cottingley Station footbridge, first larger 6 pin piles either side of bridge, then view towards White Rose station:
View attachment 169489
View attachment 169490
View attachment 169491
View attachment 169492
There were no piles on the Leeds side of the Cottingley footbridge or in/behind Cottingley station, or visible between the end of Cottingley's platforms and the M621.
Now the view from either side of Churwell Viaduct of White Rose station, showing the ladder style masts on both sides of the station, and a lone tubular mast with (shorter) jib/beam at the Morley side of the viaduct on the Leeds-Bound line:
View attachment 169493

== Doublepost prevention - post automatically merged: ==

View attachment 169494
View attachment 169495
View attachment 169496
View from Broad Oaks Farm, looking northwards towards Leeds and the White Rose station:

View attachment 169497
Note the three different mast types in this run, I'm calling them skinny I beam, fat I beam and ladder in absence of the correct terminology!
View attachment 169498
View attachment 169500
Next three pictures from taken on the opposite (northern) side of the line:

View attachment 169501
View attachment 169502
View attachment 169503
The mast above is between the White Rose centre network access gate, and the White Rose station site. I pushed as far as I could, but the footpath naturally becomes massively overgrown as it is fenced off by the arch tunnel at the station site and has therefore seen no foot traffic for years.
This style of mast, without its beam is present at either side of the White Rose centre footbridge:

== Doublepost prevention - post automatically merged: ==

View attachment 169504
View attachment 169505
View attachment 169506
We now look towards Morley/Huddersfield from the White Rose centre footbrige:
View attachment 169507
Note the same tubular mast, but with a longer Jib and no pile opposite suggesting it will carry both lines catenaries, with the odd "skinny I-beam" mast between them.
View attachment 169508
Close-ups of the tubular style mast and adjustable height jib in a medium length:
View attachment 169510
View attachment 169511
View from just above the new Daisy Hill Network Rail access gate towards the Natasha Elliot footbridge:
View attachment 169512
And the reverse view back towards the Daisy Hill gate:
View attachment 169514

== Doublepost prevention - post automatically merged: ==

Notice, two different sizes of I-beam, in different orientations. Wild how many different types of parts there are in this scheme.View attachment 169515


View towards Morley station from the Natasha Elliot footbrige, showing the last mast on this run, another tubular one with the shortest version of the jib attached:
View attachment 169517
View attachment 169518
View attachment 169519
The piles above, with boards on top appear to be the last they had done at this point, with none in/behind Morley station as per Cottingley presumably as suggested they are doing the easiest piles first:
View attachment 169521

As others have noted, they have made great progress during this blockade, its really exciting to see it all coming together.

This week Monday - Friday is the final blockade in the run, so will have another wander next weekend to see what's changed.
Thank you for this extensive documentation!

This is the first I have seen of the OLE progress between Morley and Leeds and it certainly looks promising.
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,856
Location
west yorkshire
Went for another walk on Sunday 17/11/24 to check what had changed.

Walked down the footpath from Gelderd Rd towards the Ring Road bridge, nothing to see.

View towards Ring Rd/Leeds from the Gelderd Rd bridge:

View attachment 169485
View attachment 169486
View towards the M621/Cottingley from Gelderd Rd Bridge:
View attachment 169487
VView attachment 169488
View from Cottingley Station footbridge, first larger 6 pin piles either side of bridge, then view towards White Rose station:
View attachment 169489
View attachment 169490
View attachment 169491
View attachment 169492
There were no piles on the Leeds side of the Cottingley footbridge or in/behind Cottingley station, or visible between the end of Cottingley's platforms and the M621.
Now the view from either side of Churwell Viaduct of White Rose station, showing the ladder style masts on both sides of the station, and a lone tubular mast with (shorter) jib/beam at the Morley side of the viaduct on the Leeds-Bound line:
View attachment 169493

== Doublepost prevention - post automatically merged: ==

View attachment 169494
View attachment 169495
View attachment 169496
View from Broad Oaks Farm, looking northwards towards Leeds and the White Rose station:

View attachment 169497
Note the three different mast types in this run, I'm calling them skinny I beam, fat I beam and ladder in absence of the correct terminology!
View attachment 169498
View attachment 169500
Next three pictures from taken on the opposite (northern) side of the line:

View attachment 169501
View attachment 169502
View attachment 169503
The mast above is between the White Rose centre network access gate, and the White Rose station site. I pushed as far as I could, but the footpath naturally becomes massively overgrown as it is fenced off by the arch tunnel at the station site and has therefore seen no foot traffic for years.
This style of mast, without its beam is present at either side of the White Rose centre footbridge:

== Doublepost prevention - post automatically merged: ==

View attachment 169504
View attachment 169505
View attachment 169506
We now look towards Morley/Huddersfield from the White Rose centre footbrige:
View attachment 169507
Note the same tubular mast, but with a longer Jib and no pile opposite suggesting it will carry both lines catenaries, with the odd "skinny I-beam" mast between them.
View attachment 169508
Close-ups of the tubular style mast and adjustable height jib in a medium length:
View attachment 169510
View attachment 169511
View from just above the new Daisy Hill Network Rail access gate towards the Natasha Elliot footbridge:
View attachment 169512
And the reverse view back towards the Daisy Hill gate:
View attachment 169514

== Doublepost prevention - post automatically merged: ==

Notice, two different sizes of I-beam, in different orientations. Wild how many different types of parts there are in this scheme.View attachment 169515


View towards Morley station from the Natasha Elliot footbrige, showing the last mast on this run, another tubular one with the shortest version of the jib attached:
View attachment 169517
View attachment 169518
View attachment 169519
The piles above, with boards on top appear to be the last they had done at this point, with none in/behind Morley station as per Cottingley presumably as suggested they are doing the easiest piles first:
View attachment 169521

As others have noted, they have made great progress during this blockade, its really exciting to see it all coming together.

This week Monday - Friday is the final blockade in the run, so will have another wander next weekend to see what's changed.
Thanks most interesting excellent progress.
Let's hope progress can be maintained when it comes to the testing and paper shuffling stage at the end.
Looks like concrete piles may becoming the norm.
K
 

Jamesrob637

Established Member
Joined
12 Aug 2016
Messages
6,055
This weekend is a blockade through Morley, but further blockades must be scheduled for 2025. It looks like trains are scheduled again that way from next week.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Went for another walk on Sunday 17/11/24 to check what had changed.

Walked down the footpath from Gelderd Rd towards the Ring Road bridge, nothing to see.

View towards Ring Rd/Leeds from the Gelderd Rd bridge:

View attachment 169485
View attachment 169486
View towards the M621/Cottingley from Gelderd Rd Bridge:
View attachment 169487
VView attachment 169488
View from Cottingley Station footbridge, first larger 6 pin piles either side of bridge, then view towards White Rose station:
View attachment 169489
View attachment 169490
View attachment 169491
View attachment 169492
There were no piles on the Leeds side of the Cottingley footbridge or in/behind Cottingley station, or visible between the end of Cottingley's platforms and the M621.
Now the view from either side of Churwell Viaduct of White Rose station, showing the ladder style masts on both sides of the station, and a lone tubular mast with (shorter) jib/beam at the Morley side of the viaduct on the Leeds-Bound line:
View attachment 169493

== Doublepost prevention - post automatically merged: ==

View attachment 169494
View attachment 169495
View attachment 169496
View from Broad Oaks Farm, looking northwards towards Leeds and the White Rose station:

View attachment 169497
Note the three different mast types in this run, I'm calling them skinny I beam, fat I beam and ladder in absence of the correct terminology!
View attachment 169498
View attachment 169500
Next three pictures from taken on the opposite (northern) side of the line:

View attachment 169501
View attachment 169502
View attachment 169503
The mast above is between the White Rose centre network access gate, and the White Rose station site. I pushed as far as I could, but the footpath naturally becomes massively overgrown as it is fenced off by the arch tunnel at the station site and has therefore seen no foot traffic for years.
This style of mast, without its beam is present at either side of the White Rose centre footbridge:

== Doublepost prevention - post automatically merged: ==

View attachment 169504
View attachment 169505
View attachment 169506
We now look towards Morley/Huddersfield from the White Rose centre footbrige:
View attachment 169507
Note the same tubular mast, but with a longer Jib and no pile opposite suggesting it will carry both lines catenaries, with the odd "skinny I-beam" mast between them.
View attachment 169508
Close-ups of the tubular style mast and adjustable height jib in a medium length:
View attachment 169510
View attachment 169511
View from just above the new Daisy Hill Network Rail access gate towards the Natasha Elliot footbridge:
View attachment 169512
And the reverse view back towards the Daisy Hill gate:
View attachment 169514

== Doublepost prevention - post automatically merged: ==

Notice, two different sizes of I-beam, in different orientations. Wild how many different types of parts there are in this scheme.View attachment 169515


View towards Morley station from the Natasha Elliot footbrige, showing the last mast on this run, another tubular one with the shortest version of the jib attached:
View attachment 169517
View attachment 169518
View attachment 169519
The piles above, with boards on top appear to be the last they had done at this point, with none in/behind Morley station as per Cottingley presumably as suggested they are doing the easiest piles first:
View attachment 169521

As others have noted, they have made great progress during this blockade, its really exciting to see it all coming together.

This week Monday - Friday is the final blockade in the run, so will have another wander next weekend to see what's changed.
What a detailed set of photos! Based on experience putting OLE in, I can try and piece together what I can make out from them.

Image "mly01": I've annotated the foundation types based on what sort of mast will go on them. It looks to me as if an overlap (where one wire run pair ends and another begins) is due to go in here. The "SSA" stands for "Simply Supported Anchor", and has the web of the mast (i.e. the long part of the "I") parallel to track to resist the tensile forces of the anchored wire runs.
The "TTC" stands for "Twin Track Cantilever", a mast that covers two (or more!) tracks. These are the "tubular mast and jib" structures alluded to in your posts nearer Daisy Hill/the Natasha Elliot Footbridge.
At this specific location, the TTCs will each support two cantilevers per track (i.e. 4 dangly bits overall).
mly01.jpg

Image "mly02": Another possible TTC foundation south of the overlap in "mly01". The concrete is presumably still curing.
mly02.jpg

Image "mly03": The foundation on the Up side is likely to be a standalone "STC" (Single Track Cantilever), while the one on the Down side is more likely to be an SSA (based on the arrangement of the anchor bolts parallel to track).
mly03.jpg

Image "mly04": I can make out three Dn side TTC foundations (looking almost ready to take masts) between the lens and the signal. Again, the arrangement of the holding-down bolts gives it away.
mly04.jpg

Image "mly05": The TTC bolt arrangement is clearly shown. Picture it like a pair of parentheses parallel to track: "() ||"
mly05.jpg

Image "mly06": A repeat of the arrangement in "mly03".
mly06.jpg

Image "mly07": 3 (possible) TTC foundations (all on the Dn), but this time they've gone for hydraulically-driven piles, 610mm in diameter. My hunch as to why they're TTCs is that the SSA in "mly06" is anchoring the earth wire (EW; more on them later) before the footbridge at Cottingley, so that would imply an SSA on both sides in "mly06" if the masts beyond weren't TTCs. There also appears to be a foundation on the Up for a possible Portal structure, likely to be used as a Mid-Point Anchor (MPA). Time will tell if it is!
mly07.jpg

Image "mly09": The pair of masts in the middle of the picture are the "legs" for a Portal structure. Portals are common around stations as it's easier to have a smaller live envelope around the OLE if you support the wires from the centre of the "boom" or "bridge" of the structure. There are also safety stipulations which necessitate their use around stations but to avoid further muddying the waters with railway jargon, I'll let them slide for now.
mly09.jpg
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,452
Location
Preston Lancs
Good lord! The quality of some of the posts on this thread and on this whole forum is beyond amazing at times. Thanks to everyone. Keeps me in the loop here in the USA.
 