what is happening at carstairs?Most of the electrification (and S&T and track) installation staff & plant in Scotland are at Carstairs until that is commissioned which is likely the cause of the delay.
See its thread:what is happening at carstairs?
The majority of the piles and structures were completed ahead but there is still a vast amount of OLE works to be completed within the current stages to support the changed track layouts.I thought that all the new piles at Carstairs had been done in advance of the main project.
Was at Story Contracts on Thursday and they were sending out a Piling RRV and trailers to Robslee Drive Compound which is used for working from for this work. On Wednesday Quattro had an RRV and trailers on. A good quantity of piles could be seen in the compound.In a post on Facebook today, Network Rail have stated that piling work between Thornliebank and Busby, which should have started by now, has been delayed until the end of June.
Was at Story Contracts on Thursday and they were sending out a Piling RRV and trailers to Robslee Drive Compound which is used for working from for this work. On Wednesday Quattro had an RRV and trailers on. A good quantity of piles could be seen in the compound.
Would have thought now that a good deal of the work at Carstairs has been carried out that some more time and machines would be available to concentrate on this part of the project
Several Quattro RRVs sitting in the compound at Nitshill this morning that weren't there yesterday, so hopefully a bit of progress is made on installing the last of the masts on the Barrhead route this weekend
The crazy bit of irnory is the Babcock Cranes are on site and could have been used on piling when not doing trackork. Their wiring train has been siting at Polnadie for many months. Doesn't really fill me with confidence of Projevt Planning skills.Was at Story Contracts on Thursday and they were sending out a Piling RRV and trailers to Robslee Drive Compound which is used for working from for this work. On Wednesday Quattro had an RRV and trailers on. A good quantity of piles could be seen in the compound.
Would have thought now that a good deal of the work at Carstairs has been carried out that some more time and machines would be available to concentrate on this part of the project
The wiring train hasn't been used on projects since SDA one. Also told coming in too high in hiring in costs.The crazy bit of irnory is the Babcock Cranes are on site and could have been used on piling when not doing trackork. Their wiring train has been siting at Polnadie for many months. Doesn't really fill me with confidence of Projevt Planning skills.
Example of some of the piling work requiring to be carried out during the blockade. The Piling on the Down side, pic 1 are 12mtrs deep & 14mtrs on the Up Side. Make up is Top Soil, sand, coal and then clay before solid groundThe majority of the piles and structures were completed ahead but there is still a vast amount of OLE works to be completed within the current stages to support the changed track layouts.
Q. Where will the rolling stock come from given no new order has been placed?
A. Not our problem, one for Scotrail and Transport Scotland to resolve.
If ground conditions are a problem .cast base could be used.I went along to the information session at Giffnock Library this afternoon. Sadly I knew more about the project than the Network Rail staff I spoke to did or were prepared to discuss.
On a few specifics :
Q. When will the piling start on the EK branch?
A. At the end of June. The three to four month delay is due to encountering problematic ground conditions on the Barrhead line which will take until then to resolve.
Q. Where will the rolling stock come from given no new order has been placed?
A. Not our problem, one for Scotrail and Transport Scotland to resolve.
Q. Is it still planned to have a second platform at EK?
A. No, the line will be single track. (I know …. but it wasn’t worth pursuing).
Q. What plans are in place for the numerous arched bridges on the branch.
A. No plans in place yet.
I pressed them on their lack of knowledge on the project and they admitted that they were just there to field questions on the piling as it will be noisy and intrusive. A bit of box ticking?
I’m assuming the solution you refer to is something other than complete demolition and replacement, can you elaborate on what it is?A solution for arched bridges is available and has been used in the Sourh.
I’m assuming the solution you refer to is something other than complete demolition and replacement, can you elaborate on what it is?
Many thanks, very interesting.![]()
Bridge lift could solve Network Rail electrification woes | New Civil Engineer
ElevArch rail business development manager John Kennils said it would be possible to avoid demolishing the bridge by jacking it up to create the requiredwww.newcivilengineer.com
This is an article in New Civil Engineer in August 2018
![]()
Bridge lift could solve Network Rail electrification woes | New Civil Engineer
ElevArch rail business development manager John Kennils said it would be possible to avoid demolishing the bridge by jacking it up to create the requiredwww.newcivilengineer.com
This is an article in New Civil Engineer in August 2018
It should be pointed out that arch jacking has been done only 1 time, and that was on a line closed for reconstruction. There's a timelapse somewhere that shows it isn't a quick process and involves closure of road and railway for a substantial time, while not being immune from risk as the arch can shift while jacking or settle after jacking, and an arch bridge's strength is inherently tied to the integrity of the structure - 1 brick out of place can fundamentally weaken the structure to such a point that it will eventually fail.Many thanks, very interesting.
Guess thst is a ridk you take with the process. Cant see any alternative to close both road and rail to carry it out.It should be pointed out that arch jacking has been done only 1 time, and that was on a line closed for reconstruction. There's a timelapse somewhere that shows it isn't a quick process and involves closure of road and railway for a substantial time, while not being immune from risk as the arch can shift while jacking or settle after jacking, and an arch bridge's strength is inherently tied to the integrity of the structure - 1 brick out of place can fundamentally weaken the structure to such a point that it will eventually fail.
AIUI the problem was not the bridge in isolation but its proximity to the level crossing which made the wire gradient too steep. A combination of solutions was used to ease the gradient slightly that it was acceptable with an enhanced maintenance regime (but I can't remember what all of them are).The bridge at Steventon, which is central to the way NCE presents that report, remains unlifted and, as far as I know, physically unmodified. The saga of that bridge has received much coverage on this forum and in publications such as Modern Railways.
Tubular steel piles have been driven at Busby Junction and other types of piles/foundations have been built in the rock cuttings. Masts are still to be erected on these piles.Not many gaps in the masts now
pollokshaws West on bridge over the White Cart Between Barrhead Road and Busby Junction. Possibly the cutting just after Priestley & Darnley Station. The Levernwater Bridge Arches, Rest of Viaduct completed and through to Barrhead Station Throat. Nothing in Station.

There is an additional mast on Priesthill & Darnley Station. Plus an additional pile next to the over bridge. This indicates that wires will go through under the bridge and no need for demolition and replacement.Tubular steel piles have been driven at Busby Junction and other types of piles/foundations have been built in the rock cuttings. Masts are still to be erected on these piles.
The first bracket is on the Pollokshaws Viaduct.
View attachment 133653
I found this in a presentation on Paisley Canal electrification.Arch jacking can only be used if there are no services under the roadway. Which is quite rare, it seems.

IIRC, all new schemes have to comply with the standards set out in GL/RT1210 (unless a derogation is applied for).Also issues with wire gradients and drainage between the bridges and station platform.
1/2 A bracket has appeared on the park side of the line. Hefty pieces of kit.Tubular steel piles have been driven at Busby Junction and other types of piles/foundations have been built in the rock cuttings. Masts are still to be erected on these piles.
The first bracket is on the Pollokshaws Viaduct.
View attachment 133653