It's been said before, you pay for ground inspections whether you do them or not.
As Bam found out on Sheffield University social science building, piles started sinking, whole concrete shell had to be taken down, new piles and rebuilt.
Back to Nuneham, does rather make you wonder if bored piles filled with concrete that grip irregular drilled holes would be safer for electrification masts than using wobble (vibrate) them in smooth tubes and hope they grip.
Would be rather sensible to do as many mast bases as possible whilst line is shut. Before anyone goes can't do that as its unplanned expenditure, none of what is being done now was planned expenditure. The design for where masts go was all worked out about 8 years ago before work was stopped about 5 years ago.