HS2 Ltd has updated the TBM positions in the Chiltern and Northolt tunnels, for November 29.
The Chiltern pair are at 7630m/7419m, and are moving at a good rate of over 25m/day, approaching the Amersham vent shaft.
The Northolt TBMs are at 264m and 57m, both moving slowly after their recent launch.
After a month, the backup train of the second Northolt TBM Caroline has not yet cleared into the tunnel section, but at least its position is now visible on the map.
The logistics support for these TBMs at West Ruislip will not be fully installed until the new year (railway siding, conveyor system etc).