When/if they ever re-build this route into Portishead, will they lower the new track at bridges in order to allow clearance for possible future electrification?
That's not part of the phase 1 works but has been costed under the phase 2 proposal which is a further £60m over and above the phase 1 cost of £116m.
I recall from the planning applications that various work compounds need to established strengthening works in the section from Pill to Ashton Court. IIRC 15? underbridges need works to bring them up-to standard for passenger use mostly in the various SSSI's / SAC's. Quarry underbridge 22 needs the deck replacing with the methodology requiring formation of a new access road to the compound for the works, proposal is to use a precast deck lifted into place. The Gorge area needs work on the rock faces, some cutting back, pinning and general slope stabilisation works all in the, all quite obviously in the Gorge SSSI area.
If no one will fund the costs of such unnecessary delays, then there simply can't be any costs associated when no money exists to be wasted on them.
Now in the real world its up to the applicant to fund their application and provide an adequate level of detail to alleviate concerns raised by any statutory consultees, it seems somewhat unclear what the remaining environmental concerns are currently.
I would suspect the underlying issue is that five rounds of consultation have been needed for agreement to reached from all the statutory consultees and other key consultees. Then the secretary of state then not unreasonably needing a number of months to prepare a final report having reviewed all the further submissions from the applicant and writing up the accompanying decision note to consent.
The SoS did at one stage write to the applicant (North Somerset Council) asking them to resubmit the book of reference with the numerous identified anomalies corrected, its not unusual for books of reference to be have anomalies. Indeed the SoS writing asking for these to be corrected is a fairly positive sign that application is going to be consented eventually. The book of reference would be cited in any attempt for a judicial review.
The broad topic of environmental grounds is one of the few reasons that a party not happy with the decision could try and mount a case for judicial review, so an area where the SoS will want to ensure any decision to grant or deny is watertight.
The difficulty of course with sorting out all the paperwork and process prior to consenting being that certain works are best done in the spring a summer period rather than autumn and winter, and moreover that works done in areas subject to nesting birds can only be done outside of nesting season. As just two examples where unfortunate delays can result in additional cost. These are not unusual so shouldn't be unexpected.