This is a misquote. In fact they,not sure if ORR or DFT,said that a compelling case would have to be made for more third rail routes. Checked when the issue was brought up here the usual multiple times. UK Officialdom is a lot more flexible than the AC pair who denounce & ridicule anyone who dares suggest that DC has merits in a few limited situations.
Here we go again. I'm wrong as usual. (I'm assuming I'm part of the 'AC pair' judging by the tone of your comments, yet again).
I'd be interested to read the document that says they (ORR or DfT) will permit third rail 750V DC when a compelling case exists, and also what the date on the document is.
I only ask because I've got, on my desk, a document entitled
"The UK National Implementation Plan for the Energy TSI" (dated November 2014 and updated in light of the Hendy Review and electrification delivery re-profiling earlier this year)
which specifically states (page 5 - paragraph 4.3)
The UK has published National Technical Rules for the AC and DC subsystems and these will be notified. There is no intention to increase the size of the UK’s DC third rail network.
and which goes on to specify in Section 5 (page 6 - paragraph 5.2) - UK choice of applicable system
For all future new electrification the UK plans to use the 25 kV 50Hz system.
The UK operates a number of different subsystem configurations (25 kV AC OCL, 1.5 kV DC OCL and 660/750 V DC Conductor Rail). There is no specific intent to migrate non-target system configurations to the 25 kV AC OCL configuration but this will be considered on a case by case basis when upgrade or system renewal is required
The document specifically excludes the 750V DC third rail system from the 'UK choice of applicable system' and in "Table 1 Projects for: new lines,
work on existing electrification and new electrification on existing route" it specifically states.
There is no intention to increase the size of the UK’s DC third rail network
I don't know how much clearer that can be. I don't even know why we're arguing about this. XDM can post all he wants about what he thinks DfT/ORR have said, but Network Rail (in addition to DfT and ORR) are explicitly clear about what the documentation means and how it's being interpreted.
If XDM isn't happy, neither I nor this forum are the place for his complaints, he needs to take up the issue with the Department for Transport and the Office for Road and Rail (ORR). I can't change either what the document says or how it's being interpreted.