It was designed by Brunel and occupied by Brunel during the construction of the GWR
.Well done NR.
Brunel would be delighted to see electrification outside 'his' house. Goring is only an area of outstanding natural beauty by virtue of some bizarre legislation, it's hardly outstanding, it's not natural and it's arguable whether it's even beautiful.
The letter sent in December still has a number of problems which I pointed out to you before it was sent, and which haven't been taken on board.
The RIBA design competition entries (
http://www.ribacompetitions.com/ols/shortlisted.html) are, in every case, not viable for one reason or another, in all cases such significant work would be needed to make the designs viable for any sort of 25kV electrification system that they would look very much like the currently planned system.
There's nothing in the RIAB competition linked to in the letter which is suitable for four tracks, and which could fit the site at Goring. The designs are also grossly deceptive (that's not your fault) and build unrealistic expectations.
1. Bow - single track design, plan shows no insulator, cantilever or registration arm details. No return cable or AT cables shown.
2. The High Speed T - twin track design with central mounting, which we don't use for drainage reasons, no registration arms shown, no AT cables shown, may show return cable, but unclear.
3. Tomahawk - single track design, otherwise fully featured, but with bespoke single track cantilever which would need standardised. Not suitable for four track locations is its only real design issue.
4. VelocitY - twin track design with central mounting which we don't use, vague registration arm details, AT feed missing, bespoke catenary wire mounting an issue.
5. Tuning Fork - headspan design, unrealistic spacing, unsuitable design, unrealistic visibility for headspan in any case.
6. Needle System - almost identical to Series 1 but with a slightly 'hipper' design.
7. Origami Birds - single track design, vague registration arm details, poor catenary/contract wire fixings which wouldn't survive terribly long
8. Integrated OLS - single track design, no insulators to dissipate forces during a dewirement and no defined 'hot' and 'cold' areas for safety, so a complete non starter of a design, no return wire or AT wire shown either.
9. Responsive Overhead Line Structures - looks like something out of Harry Potter, and no less low profile than the masts up at Gatehampton Bridge or the older design on the Royal Border Bridge. Vague contact, catenary, return and AT wire details, vague registration details, vague insulator details etc.
10. Overhead Rhythmic Structures - no lower profile than Series 1, but better looking. Bespoke and very complex cantilever arms etc, much like BR Mark 1 OLE, which isn't the most reliable.
It's also untrue to say Series 1 isn't low profile - it's a considerable improvement over the old double gantry used on the GEML.
http://www.old-dalby.com/images/14-02-03_new portal frame.jpg
Now, just to recap, the design needs to be as it is - it's unavoidable.
Headspans are out for reliability and line speed improvements, we're ripping them out along by Heathrow right now (probably right now, as I type this, in fact). That leaves either single masts, twin track cantilevers or portals.
We've been over this before, no matter what the masts look like, they will be essentially the same design and have the exact same wiring. The best that can happen is they'll be pretified slightly.
The masts have a specific height about the portal or cantilever structure to attach the 25kV ATF cable in a position of safety, where an insulator failure will cause the cable where it will earth on the structure and not hit signalling or other electrification components.
There then needs to be a return cable running alongside the structure to complete the wiring circuit.
Above the track you have a catenary for each line - cantilever arm, registration arm, insulator assembly, with the contact wire and catenary wire bottom and top respectively, joined by droppers.
There needs to be tensioning at appropriate intervals, now spring loaded tensioning units from Tensorex, they're nice and tidy too, but require braced structures due to the tensions involved (16.5kN for contact wire).
The portals could be tweaked (though I think they're a fair design given the GEML double height units) but everything on or under the portal will be the same, there's no leeway at all to change wires, registration arms, insulators etc.
--- old post above --- --- new post below ---
You and many others. NR needs breaking up and put into commercial reality.
Yes, because that went ever so well the last time. It's needing to be left alone to get on with things, not perpetually pestered by communities who want a certain type of line, signal box, crossing gate, station or type of train (believe me, we've had the lot).