The Office of Rail and Road (ORR) published its findings on Friday 16th Oct from its investigation into Network Rail's performance after multiple deadlines were missed in the ambition programme of capacity improvements in the current control period.
Full media summary : http://orr.gov.uk/news-and-media/press-releases/2015/network-rail-is-taking-immediate-action-to-improve-planning-and-delivery-of-rail-enhancementsNetwork Rail is taking immediate action to improve planning and delivery of rail enhancements
16 October 2015
Network Rail is taking action to improve planning and delivery of rail enhancements, the Office of Rail and Road (ORR) concluded today. This follows the regulator's investigation into the company's delivery of a multi-billion pound enhancement programme on Britain's railways.
Network Rail committed to deliver a challenging £13bn enhancements portfolio to improve performance and capacity on Britain's railways, in its current funding period between 2014-2019. In November 2014, ORR raised concerns about project deliverability and cost increases, and after a significant number of milestones were missed, launched an investigation in March 2015 to understand the reasons for enhancements going wrong.
ORR's investigation found systemic weaknesses in Network Rail's handling of its enhancement programme including poor processes for setting initial project requirements, no defined framework for managing complex programmes, a lack of portfolio management capability and low productivity. Together these issues have resulted in significant underestimates of project timescales, and impacted on operational performance and costs.
In response to ORR's investigation findings, Network Rail has worked with the regulator to identify and address its weaknesses through the development of an enhancement improvement plan. The plan will drive improvements in the way Network Rail manages its relationships with project sponsors, ensure safety is considered at a design stage, and reform how costs and risks are estimated, alongside changes in project governance, deliverability assessment and monitoring.
ORR will hold Network Rail to account for delivering the improvements needed, ensuring the plan is fit for purpose and put into practice. While it will be a significant and long-term challenge for the company to integrate and embed the improvements into business as usual, they are essential to protect the investment which is being funded by taxpayers, passengers and freight customers.